Plan shipment tasks on a Gantt chart

Guide information

Audience: Operations lead (reschedules tasks); Operations staff only need to read the chart for their own tasks
Time required: about 5 minutes
Outcome: every shipment task on one Gantt chart, with a task’s dates moved by dragging its bar when a schedule changes

Requirements

This tutorial requires the installation of the following applications/modules:

An Operations lead runs several shipments at once, each with 5-7 operational tasks - booking, documentation, customs, delivery - generated from a project template (see Run shipment tasks in a project). A list or kanban view of these tasks has no timeline, so seeing who is overloaded on a given day means opening each task one by one. The Gantt chart plots every shipment’s tasks on one axis instead, so an overlap is visible at a glance, and dragging a bar reschedules the task the moment something upstream changes - a vessel sailing later, for example.

Running scenario: Hai Long Logistics’s export shipment SHP/2611/00005 for Phuoc An Wood Co., Ltd sails later than planned. Duc (Operations Manager) reschedules the shipment’s Original B/L (Telex) release task so that it falls after the new loading date. The records are the Viindoo demo data, so yours will differ.

Before you start

  • The shipment already has a project with tasks generated from a template - see Run shipment tasks in a project.

  • The tasks already carry real planned dates. A newly generated task gets Planned Start Date = the moment it was created, so its bar sits on the shipment’s creation date until someone plans it. Plan each task on its deadline before you use the chart to compare workloads.

  • You are in the User: Own Shipments group or above, to see the Tasks menu, and also in the Project: User group - the Freight access levels do not grant Project access on their own.

See also

Run shipment tasks in a project for how a shipment’s tasks are generated from a template in the first place.

Note

Dragging a task on the Gantt chart does not notify whoever is assigned to it. Tell the team through the chatter or an internal channel when a reschedule needs to reach them quickly.

Step 1: Open the Shipment Tasks Gantt chart

Every shipment’s tasks need to land on one timeline before an overlap becomes visible, so the chart has to show more than the shipment you are currently working on.

Go to Freight Forwarding ‣ Tasks ‣ Shipment Tasks, then click the Gantt Chart icon on the view switcher.

After you click the Gantt Chart icon:

  • Every shipment task appears as a bar on the timeline, colored by its stage - the chart is not grouped by shipment or by stage by default.

  • Use Day, Week, Month or Year to change the time scale, and Today to jump to the current date.

  • Use Group By on the search bar if you want the bars grouped, for example by shipment.

Tip

Step 1 is done when: the tasks of shipment SHP/2611/00005 show as bars on the chart, with Original B/L (Telex) release among them.

Decide which task list to plan from

Option

Use when

What changes

Shipment Tasks

Planning for the whole team, across every open shipment

The chart includes every user’s tasks, not filtered by who is assigned

My Tasks

Checking or rescheduling only your own tasks

The chart keeps only the tasks where you are one of the assignees

Use Shipment Tasks for a team-wide review and My Tasks for your own workload. Check the selected view before rescheduling so you do not move another person’s task without coordination.

Step 2: Reschedule a task by dragging its bar

The booking of SHP/2611/00005 rolled over to a later sailing (see Handle rolled-over and not-loaded containers), so the loading date moved. The Original B/L (Telex) release task is still planned on its old date on the chart - a date before the cargo has even been loaded, since the B/L can only be released once loading is confirmed.

Drag the bar for Original B/L (Telex) release to the right until it lands the day after the new loading date, or open the task and set the two fields by hand:

  • Planned Start Date: the day after the new loading date.

  • Planned End Date: the same day.

After you drop the bar in its new position:

  • The bar moves immediately to the new dates on the chart.

  • Planned Start Date and Planned End Date are written straight to the task - there is no separate confirmation step.

Warning

Dropping the bar so that its end lands before its start - by dragging the wrong edge, or typing the dates in the wrong order - is rejected on save. See Troubleshooting.

Tip

Step 2 is done when: the Original B/L (Telex) release bar sits after the new loading date - no bar for this task remains before the vessel has sailed.

Known limitations

Step

What Viindoo does today

What you do instead

Tell the assignee about a new date (Step 2)

Dragging a bar changes the dates without notifying the people assigned to the task

Post in the task’s chatter or tell them directly

Resolve an overlap (Step 2)

The chart flags a person’s overlapping tasks but never reassigns anyone

Change Assignees on one of the tasks yourself

Troubleshooting

Dragging a task reports an error about the dates

Symptom: “The Planned Start Date must be earlier or equal to the Planned End Date”.

Cause: the drag (or a manual edit) left the end date earlier than the start date.

Fix: drag the bar again in the right direction, or open the task and correct Planned Start Date and Planned End Date by hand so the start comes first.

The Gantt Chart icon does not appear on the view switcher

Symptom: opening Shipment Tasks or My Tasks shows a view switcher with no Gantt icon.

Cause: the Project and Timesheets apps were not installed when Freight Sale was, so Freight Project & Operations Tasks and Freight Project Gantt never installed (see Requirements).

Fix: install Freight Project Gantt (see Requirements). Until then, reschedule by editing Planned Start Date and Planned End Date on the task.

A rescheduled task still shows its old assignee, even though the new date overlaps another task

Symptom: after dragging a task to a new date, the person assigned to it is unchanged, even though the chart now shows two of their tasks on the same day.

Cause: the Gantt chart warns about this - it counts each user’s overlapping tasks and shows an alert such as “1 other tasks for employees are scheduled at the same time!” - but it never reassigns anyone by itself.

Fix: read the overlap alert on the task, then reassign one of the two tasks to someone else by changing its assignees, if the overlap is a real conflict.