How to manage your personal and private tasks

When you work on several projects, your tasks are spread over many boards. My Tasks gathers every task assigned to you in one screen, sorted in your own stages. You can also create private tasks: tasks without a project that only you see. The To-do app keeps the same private tasks as a simple list of memos.

Task

Role needed

Where

Follow your assigned tasks and your private tasks

Any internal user. Project: User or Project: Administrator to work on the tasks of a project

Project ‣ Tasks ‣ My Tasks

Keep quick to-dos and turn one into a project task

Any internal user

To-do

Before you start

What does My Tasks show?

Go to Project ‣ Tasks ‣ My Tasks.

The My Tasks screen with the tasks in personal stages
  • The screen lists the tasks assigned to you in all the projects, and your private tasks.

  • The columns are your personal stages: Inbox, Today, This Week, This Month, Later, Done and Cancelled. They are yours: another user does not see them, and moving a task to Today does not change its stage in the project.

  • Click Personal Stage at the right of the last column to add a stage of your own.

  • A lock on a card marks a private task.

  • The buttons at the top right show the tasks as a list, calendar, pivot, graph, activity view or Gantt chart. Use the filters and search to find a task.

How do I create a private task?

  1. Go to Project ‣ Tasks ‣ My Tasks and click New.

  2. Type the title of the task.

  3. Leave the Project field empty. The field shows Private.

  4. Fill in the other fields as for any task, see how to create a task, then click Save.

    A private task whose Project field shows Private

The task goes to your personal stage and only you can see it. Choose the project later to turn it into a task of the project.

How do I organise my tasks on a calendar?

Click the calendar icon. Each task appears on its deadline. Click a date to create a task, or drag a task to another date to move its deadline.

My Tasks in the calendar view

How do I follow the activities I planned?

Click the activity icon. The grid lists your tasks with the activities planned on them, by type, so you see what to do next. Click Schedule activity to plan a new one. See Schedule activities.

My Tasks in the activity view

How do I see my tasks on a timeline?

Click the Gantt chart icon. Each task is a bar between its planned start and its planned end, coloured by stage. Drag a bar to change the dates, and follow the arrows between tasks that depend on each other. See How to follow the progress of your projects.

My Tasks in the Gantt view

How do I keep quick to-dos in the To-do app?

Open To-do from the main menu. A to-do is a private task shown as a simple card: a title, the assignee, the tags and a free text. The to-dos are in the same personal stages as in My Tasks.

The To-do app with the to-dos in personal stages

To turn a to-do into a task of a project:

  1. Open the to-do.

  2. Click the gear icon next to its title, then Convert to Task.

  3. Choose the Project, and the Assignees and Tags if needed, then click Convert to Task.

    The Convert to Task window of a to-do

The task opens in its project, and the to-do is no longer private.

Common errors

Problem

What to do

You cannot edit the tasks assigned to you.

Give the user the User or Administrator right in the Project line of the access rights.

The Gantt chart icon is missing.

Tick Task Logs in the settings of the Project app.

A private task is missing from the screen.

Remove the Open Tasks filter: a task you closed is hidden by it.

A colleague cannot see your private task.

This is expected. Choose a project on the task to share it.

Next steps