Manufacturing report in Gantt¶
The Gantt view shows the manufacturing orders and work orders on a timeline: what runs when, in which state, for whom and on which work center. You see at a glance what is late or overlaps.
Who |
Production managers and planners with the Manufacturing ‣ User access right. |
App |
Manufacturing |
Before you start
Install the Manufacturing app. The Gantt view comes with the Viindoo Manufacturing module, installed with it.
The work orders need the Work Orders setting, see Manage Manufacturing process in Viindoo.
How do I see the manufacturing orders in Gantt?¶
Go to Manufacturing ‣ Operations ‣ Manufacturing Orders and click the Gantt icon at the top right.
Each bar is an order, from its start to its end. Choose the scale (day, week, month), and filter and group by product, state or responsible.
Group by state to count the orders confirmed, in progress or to close, and find the ones at risk of being late with their responsible.
How do I see the work orders in Gantt?¶
Go to Manufacturing ‣ Operations ‣ Work Orders and click the Gantt icon.
The work orders are grouped by work center: you see the load of each one, avoid overlaps and spread the work.
Manufacturing ‣ Planning ‣ Work Orders opens the same work orders planned by production or by work center.
Common errors¶
Problem |
What to do |
|---|---|
The Gantt icon is missing. |
Install the Viindoo Manufacturing module. |
An order is not on the chart. |
It has no dates in the period shown, or a filter hides it: change the scale or remove the filters. |
The Work Orders menu is missing. |
Turn on Work Orders in the settings. |
Next steps¶
How to understand manufacturing reports: the other manufacturing reports.
Create and use Alternative Work Centers: more capacity for a busy work center.