Viindoo demo handbook for manufacturing and assembly
Part IV. Purchasing and import
Lessons in this part
- Lesson 22. Purchasing and import configuration in use
- Lesson 23. Import purchase order in a foreign currency
- Lesson 24. Check material availability and buy the shortfall for a manufacturing order
- Lesson 25. Supply request and approval
- Lesson 26. Purchase order approval threshold
- Lesson 27. Import costs in inventory cost
- Lesson 28. Vendor bills and payables
- Lesson 29. Purchasing and import reports
- Lesson 30. Exercise: receive an import batch of components from start to finish
This part answers these questions: where do you buy the components you are short of, how do you buy in a foreign currency, do large orders have to be approved, and do import duty, freight and customs fees go into the cost of each component? It is written for purchasing staff, planners, storekeepers and accountants.
Every hands-on lesson starts with your company creating its own documents (purchase order, request, manufacturing order). Your company does not have to edit records that belong to someone else.
Note on typing numbers: type decimal numbers with a dot, for example
1.05for a unit price of 1.05.
Lesson 22. Purchasing and import configuration in use
About 10 minutes. By the end of this lesson your company knows what is switched on in the system for purchasing and importing, and what is lost if it is switched off.
Step 1 - Read the Purchase settings
Open Purchase, go to Configuration and click Settings. Read the Orders group (read only, do not click Save).
Purchase > Configuration > Settings
What you should see: the Purchase Order Approval box is not ticked; Purchase Agreements (with Purchase Alternatives under it) and Receipt Reminder are ticked.
Step 2 - Read the supply routes
Open the list of routes. Find the two lines Buy and Buy - Foreign Import.
Inventory > Configuration > Warehouse Management > Routes
What you should see: the list has a Buy route and a Buy - Foreign Import route. The second route sends goods to the customs clearance area instead of straight into the warehouse.
Step 3 - Read the import operation types
Open the list of operation types and scroll to the bottom. Find Import - Customs Clearance Area and Import - Goods Receipt of Nhà máy Yên Mỹ (Yen My Factory).
Inventory > Configuration > Warehouse Management > Operations Types
What you should see: two import operation types that belong to Nhà máy Yên Mỹ, placed after the ordinary receipt, delivery and manufacturing types.
Step 4 - Read the vendor price list on a product
Open the product Lithium Battery 60V-30Ah and choose the Purchase tab.
Purchase > Products > Products
What you should see: every vendor has its own Quantity (the minimum quantity), Price, Currency and delivery lead time. Foreign vendors are priced in USD or CNY (here Zhejiang Lianfeng at 238.00 USD for 50 units), domestic vendors in VND.
Step 5 - Read the purchase approval type
Open the approval type Component Purchase Order over 500 Million.
Approval > Configuration > Approval Types
What you should see: the type applies to Quotation / Purchase Order, Sequential Approvals is on, Minimum Approvals is 2, and under Extra Approval Steps there are two specific approvers in order 1, 2.
What you lose without it
| Configuration | Current state | What you lose without it |
|---|---|---|
| Purchase Order Approval (Purchase settings) | Off | A high-value purchase order is confirmed at once, with no manager approval step to stop it (see the lesson Purchase order approval threshold) |
| The Buy - Foreign Import route and the two import operation types | In place | Imported goods go straight into the warehouse, without passing through the customs clearance area, and no customs clearance request can be attached |
| Vendor price list by currency | In place | The purchase order needs a hand-typed price, with a high risk of the wrong currency or the wrong quantity tier |
| Purchase order approval type | In place | There is no multi-step approval request for large orders |
| Incoming quality control (see Part V) | In place for some product groups | Defective goods enter the warehouse without being held back |
Lesson 23. Import purchase order in a foreign currency
About 15 minutes. By the end of this lesson your company has a purchase order for components from a foreign vendor, priced in USD, confirmed, with a receipt waiting at the customs clearance area.
Step 1 - Open a new purchase order and choose a foreign vendor
Open Requests for Quotation, click New. In the Vendor field, type Zhejiang Lianfeng and select it.
Purchase > Orders > Requests for Quotation
What you should see: the Foreign Import box is ticked automatically, and Deliver To changes to Nhà máy Yên Mỹ: Import - Customs Clearance Area.
Step 2 - Choose the USD currency and add the product line
Purchase > Orders > Requests for QuotationIn the Currency field choose USD. Type MK-IV-01 in Vendor Reference. Click Add a product, type PIN-LI-60V30, select it and enter Quantity 4. Click the x in the Taxes field to remove VAT from the order (import duty and import VAT are calculated in the customs clearance request).
Purchase > Orders > Requests for Quotation
What you should see: the unit price is 238.00 (check it against the vendor price list), the order total is 952.00 USD, and the amount converted to dong (24,990,000 VND) appears on the line below.
Step 3 - Save and click Confirm Order
Click the save icon, then click Confirm Order. The Purchase Order Confirmation dialog asks for the Confirmation Date; keep today's date and click Validate.
Purchase > Orders > Requests for Quotation
What you should see: the Purchase Order Confirmation dialog with the current date and time.
Step 4 - Check that the order has become a purchase order
After confirming, look at the status bar and the buttons above it.
Purchase > Orders > Requests for Quotation
What you should see: the status is Purchase Order; the Receipt button shows 1; the Create Customs Clearance Request and Receive Products buttons appear. A small order like this one is not held for approval.
Lesson 24. Check material availability and buy the shortfall for a manufacturing order
About 20 minutes. By the end of this lesson your company can read which components of a manufacturing order are not yet available, and has ordered the missing quantity from a vendor priced in Chinese yuan.
Step 1 - Create a manufacturing order
Open Manufacturing Orders, click New. In Product choose XMD-AURA-DD-CC (Viindoo Aura Electric Motorbike (Burgundy, Premium)), enter Quantity 5. Click save.
Manufacturing > Operations > Manufacturing Orders
What you should see: Bill of Material is filled in automatically, and the Components tab lists all components for a quantity of 5.
Step 2 - Confirm the manufacturing order
Manufacturing > Operations > Manufacturing OrdersClick Confirm.
Manufacturing > Operations > Manufacturing Orders
What you should see: the status is Confirmed; the Transfers button (the component pick, showing 3) and the Overview button appear, and Component Status reads Available.
Step 3 - Open the order overview to check availability
Click the Overview button at the top of the order.
Manufacturing > Operations > Manufacturing Orders
What you should see: the finished product on the first line (status Ready, with an orange Expected date in the Receipt column) and one line per component below it. A green Available on a component line means that component is fully reserved; a component that is short shows an orange expected date instead. The Free to use / On Hand column shows how much can still be used out of the total stock, and Reserved shows how much this order has reserved. For example, Hub Motor 72V 1500W 12-inch Rim has 152 on hand but only 82 available, because the rest is reserved for other orders. The figures change from day to day; your company reads them in exactly this way.
Step 4 - Order the shortfall from a foreign vendor
Open Requests for Quotation, click New. Vendor Jiangsu Huanyu, Currency CNY, type MK-IV-05 in Vendor Reference, add the line DC-HUB-72V (Hub Motor 72V 1500W 12-inch Rim) with quantity 2, remove VAT.
Purchase > Orders > Requests for Quotation
What you should see: currency CNY, an order total of ¥1,578.29 (unit price 789.144043), and the amount converted to dong (5,808,107 VND) below it.
Step 5 - Confirm the shortfall order
Purchase > Orders > Requests for QuotationClick save, Confirm Order, then Validate in the date dialog.
Purchase > Orders > Requests for Quotation
What you should see: the status is Purchase Order, and the Receipt button shows an expected receipt linked to the order. When the goods arrive, click Check Availability on the component pick of the order to reserve the newly arrived quantity.
Lesson 25. Supply request and approval
About 15 minutes. By the end of this lesson your company sends a supply request, gets it approved, and sees the system generate the stock transfers along the supply routes.
Step 1 - Create the supply request
Open Approval, open the Approval Request menu, choose Request and click New. In Approval Request Type choose Purchase Request. Enter the Title. On the Request Lines tab click Add a line: product LK0149 (Viindoo Warranty Book), Destination Warehouse Nhà máy Yên Mỹ (Yen My Factory), Quantity 20. For the title you can write, for example, "Request to buy warranty books for this week's assembly lot".
Approval > Approval Request > Request
What you should see: the status is Draft, a Submit button, and the Approvers tab beside Request Lines.
Step 2 - Submit the request
Approval > Approval Request > RequestClick save, then click Submit.
Approval > Approval Request > Request
What you should see: the status is To Approve; the Refuse, Cancel and Force Approval buttons appear, Next Approver(s) lists who has to approve, and each approver receives a to-do in the right-hand panel.
Step 3 - Approve the request
A user with approval rights clicks Approve.
Approval > Approval Request > Request
What you should see: the status is Approved, Approval Progress 100%; the Mark as Done and Launch Procurement buttons appear, together with the smart buttons Procurement Groups (1), Receipts (1), Deliveries (1) and Stock Transfers (2). The system chooses the supply method from the route of the destination warehouse: Nhà máy Yên Mỹ is resupplied from Kho Tổng (Central Warehouse), so it generates one delivery at Kho Tổng and one receipt at Nhà máy Yên Mỹ. If Kho Tổng does not have enough stock, the delivery waits for goods.
Lesson 26. Purchase order approval threshold
About 10 minutes. By the end of this lesson your company knows how high-value purchase orders are controlled on this system.
Step 1 - Create a high-value purchase order
Create a Request for Quotation for the vendor Nhựa kỹ thuật Xuân Hòa, add the line OPS-LUMI-TR (Painted Plastic Body Kit Lumi - Pearl White) with quantity 120 and unit price 1,850,000, and type MK-IV-06 in Vendor Reference. Click save.
Purchase > Orders > Requests for Quotation
What you should see: an order total of 244,200,000 VND (222,000,000 VND untaxed plus 22,200,000 VND of 10% VAT).
Step 2 - Confirm the purchase order
Purchase > Orders > Requests for QuotationClick Confirm Order, then Validate in the date dialog.
Purchase > Orders > Requests for Quotation
What you should see: the order moves straight to Purchase Order, with no waiting-for-approval status. The reason: the Purchase Order Approval box in the Purchase settings is off (see the lesson Purchasing and import configuration in use). To make large orders go through a manager, your company switches this box on and sets a Minimum Amount; the description shown by the system reads: "Request managers to approve orders above a minimum amount".
Step 3 - Compare with the two-step approval type
Open again the approval type Component Purchase Order over 500 Million from the configuration lesson. This is a multi-step approval path for quotations and purchase orders: two approvers approve in turn, and the second one is reached only after the first has approved.
Approval > Configuration > Approval Types
What you should see: under Extra Approval Steps, two lines with the Approver Selector Specific Approvers (Trần Thị Hạnh, then Nguyễn Văn Quang), with the Required column ticked on both.
Lesson 27. Import costs in inventory cost
About 35 minutes. By the end of this lesson your company has an import batch whose import duty, sea freight and customs fees have been added to the stock value of the components, and has checked this with the valuation report.
Principle: freight and customs fees come from the service vendor's bill; import duty comes from the customs clearance request. Your company does not enter costs into stock with a hand-made entry that has no bill: an entry that credits 151 with no matching debit to 151 makes account 151 go more and more negative.
Step 1 - Create the import purchase order and confirm it
Create a purchase order for the vendor Tianjin Huaxin, currency CNY, vendor reference MK-IV-08, one line LK0188 (Front Disc Rim 2.15x10 Vepas, V6) quantity 20, keep the unit price the system fills in, remove VAT on the line. Save, click Confirm Order, then Validate in the date dialog.
Purchase > Orders > Requests for Quotation
What you should see: an order total of ¥985.34 (3,626,051 VND), and the Foreign Import box ticked automatically.
Step 2 - Receive the goods at the customs clearance area
From the purchase order click Receipt, open the transfer NM1/IMP/xxxxx, click Validate, then Validate in the Validate with a Back Date dialog.
Purchase > Orders > Requests for Quotation
What you should see: a transfer coded NM1/IMP/xxxxx in status Ready, with the buttons Validate and Create Customs Clearance Request, Operation Type Nhà máy Yên Mỹ: Import - Customs Clearance Area, and Destination Location NM1/Nhập khẩu - khu vực thông quan (NM1/Import - customs clearance area).

What you should see: the status is Done; the Next Transfer smart button (receiving the goods into the warehouse) appears. The Create Customs Clearance Request button is available on the transfer until a request exists; once it has been created (step 4), a Customs Declaration smart button showing 1 takes its place.
Step 3 - Enter the freight and customs fee bill
Open Bills, click New. Vendor Công ty TNHH Giao nhận Biển Xanh (the freight forwarder; create it if it does not exist yet). Enter the Bill Reference and the Bill Date. Add two lines: product CP-CUOC-BIEN (International Freight (Sea)) at 1,200,000 and CP-HAIQUAN (Port Customs, Handling and Storage Fees) at 800,000.
Accounting > Vendors > Bills
What you should see: two cost product lines with 10% tax: 2,000,000 VND untaxed, 200,000 VND of VAT, total 2,200,000 VND.
Click Confirm.
Purchase > Orders > Requests for Quotation
What you should see: the status is Posted; the two cost lines post to account 151 Goods in transit (debit 151 2,000,000 VND), and the Pay, Register Advance Payment and Credit Note buttons appear; a Landed Costs smart button lists the landed cost documents linked to this bill (a draft bill carries a Create Landed Costs button instead). In this lesson your company puts the costs into stock cost through the customs clearance request in a later step.
Step 4 - Create the customs clearance request
Go back to the transfer NM1/IMP/xxxxx, click Create Customs Clearance Request, then click save.
NM1/IMP/xxxxx
What you should see: the request CD/IMP/xxxxx takes the Purchase Orders, Transfers and Currency Rate automatically, in status Draft with the Open and Cancel buttons, Currency Rate 3,680.00, and a goods line carrying 10% Import Tax and 10% Import VAT with a Taxable Value of 3,981,760 VND.
Step 5 - Link the freight and customs fee bill to the extra expenses
Scroll down to Extra Expenses, click Add a line. In the Related Cost Journal Item column choose the freight line of the bill you just posted; for Split Method choose By Taxable Value. Add a second line, choose the customs fee line, split method Equal. Click save.
NM1/IMP/xxxxx
What you should see: the Expense Amount is filled in as 1,200,000 VND and 800,000 VND from the bill, and the cost product is filled in from the bill line.
Note: if you choose By Quantity when the goods lines belong to two different unit-of-measure categories (for example Set and Unit), the system shows "You can't select split method is
By Quantity, while applied products has different UoM categories." and does not save. Choose Equal or By Taxable Value instead.
Step 6 - Click Allocate Expenses
Click the Allocate Expenses button.
NM1/IMP/xxxxx
What you should see: the Expense column of the goods line goes from 0 to 2,000,000 VND; the Taxable Value column rises by the same amount, from 3,981,760 to 5,981,760 VND.
Step 7 - Open the request and confirm with customs
Accounting > Vendors > BillsClick Open, then click Confirmed by Custom.
NM1/IMP/xxxxx
What you should see: the status is Confirmed by Custom; the Journal Entries button (import duty debit 151 / credit 3333, import VAT debit 1331 / credit 33312) and the Landed Cost button show the number of documents (2 and 3 here); a Taxes Payment button appears.
Step 8 - Look at the landed cost documents
Click the Landed Cost button and open each document.
Inventory > Operations > Adjustments > Landed Costs
What you should see: a document for import duty of 562,627 VND, Posted, linked to the transfer NM1/IMP/xxxxx.

What you should see: a document for freight and customs fees totalling 2,000,000 VND, Posted, with the Vendor Bill field pointing to the freight forwarder's bill. The entry debit 152 / credit 151 of this document is offset by the debit to 151 on the bill, so 151 has no odd balance left. The Import Exchange Diff document (a small amount, a few hundred dong) may still be Draft; it is the exchange-rate difference arising when duty is computed, not yet posted.
Step 9 - Check with the valuation layers
Open the Valuation report and filter on product LK0188.
Inventory > Reporting > Valuation
What you should see: the receipt line (20 units, value 3,626,049 VND) and the lines with Quantity 0.00 under the same reference NM1/IMP/xxxxx, with values of 562,627 VND (duty), 1,200,000 VND (freight) and 800,000 VND (customs fees), plus a rounding line of 2 VND. The quantity does not change, and the stock value rises by exactly the cost: 2,562,627 VND, from 3,626,049 to 6,188,676 VND.
Step 10 - Receive the goods into the warehouse
Go back to the IMP transfer, click Next Transfer, open the transfer NM1/IMP-IN/xxxxx, click Validate and Validate in the date dialog. Then open the Storage transfer (NM1/STOR/xxxxx) and do the same.
NM1/IMP/xxxxx
What you should see: the IMP-IN transfer moves the goods from NM1/Nhập khẩu - khu vực thông quan (NM1/Import - customs clearance area) to NM1/Đầu vào (NM1/Input).

What you should see: the STOR transfer moves goods from NM1/Đầu vào (NM1/Input) to NM1/Tồn kho (NM1/Stock). While the customs clearance request has not been confirmed by customs, the IMP-IN transfer is blocked (see the lesson Receiving imports in stages).
Lesson 28. Vendor bills and payables
About 10 minutes. By the end of this lesson your company can create a vendor bill in a foreign currency from a purchase order and see the amount payable in the aged payable report.
Step 1 - Create the bill from the purchase order
Open an import purchase order whose goods have been received (for example the order for the vendor Taichung Hsinwei, two lines LK0043 (Front Hydraulic Brake Assembly Veras, Bella E) and LK0221 (Front Brake Disc VP V6, Veras), 50 each, created as in the lesson Import purchase order in a foreign currency), click Create Bill. Enter a Bill Reference of your own (for example HD-TC-MK-02B) and today as the Bill Date.
Purchase > Orders > Purchase Orders
What you should see: a draft bill linked to the purchase order, vendor Taichung, two goods lines posted to account 151 Goods in transit, total 234.84 USD.
Step 2 - Confirm the bill
Click Confirm.
Purchase > Orders > Purchase Orders
What you should see: the status is Posted, the bill number has the form HÓA Đ/2026/10/xxxxx, there is a rate line under Journal, and the Pay, Register Advance Payment and Credit Note buttons appear. If the vendor has outstanding prepayments, a blue banner reads "You have outstanding debits listed below for this vendor."
Step 3 - Read the vendor's payable balance
Open Aged Payable (it opens for all partners, as of today) and search for or expand the vendor Taichung.
Accounting > Reporting > Partner Reports > Aged Payable
What you should see: the report is dated today ("As of ...") with the columns At Date, 1-30, 31-60, 61-90, 91-120, Older and Total, one row per partner and a Total row at the top. The bill you just created sits in the At Date column of the vendor's row, converted from USD at the rate of the bill date. A negative figure is a prepayment or credit already held for that vendor, so a vendor's total can be negative: your company has prepaid more than it still owes.
Lesson 29. Purchasing and import reports
About 10 minutes. The table below lists the reports your company uses for purchasing and importing.
| Report | Path | Question it answers |
|---|---|---|
| Purchase Analysis | Purchase > Reporting > Purchase |
How much is bought, by vendor, product and month |
| Aged Payable | Accounting > Reporting > Partner Reports > Aged Payable |
Which vendors you owe, and how overdue it is |
| Partner Ledger | Accounting > Reporting > Partner Reports > Partner Ledger |
Each movement and payment for one vendor |
| Purchase Invoice List (form 01 - 2/GTGT) | Accounting > Reporting > Invoice Lists |
Input VAT declared by invoice |
| Landed Costs | Inventory > Operations > Adjustments > Landed Costs |
How much duty, freight and fees each import batch has added to cost |
| Landed Costs Analysis | Inventory > Reporting > Landed Costs Analysis |
Landed costs by product and by period |
| Valuation | Inventory > Reporting > Valuation |
Stock value of each component and the added cost layers |
| Stock-In Report | Inventory > Vietnam Legal Reports |
Goods received into stock in the period, in the statutory format |
| Incoming quality control report by vendor | Quality > Reporting > Quality Alerts |
Which vendors cause repeated defects (see Part V) |
Purchase > Reporting > Purchase
What you should see: a line chart of Untaxed Total over time, filtered on Purchase Orders or the Confirmation Date of a month; change the chart type, the measure and the grouping with the toolbar above.

What you should see: the LC/... documents with Name, Date, Company and State; a Draft document is one not yet posted.
Lesson 30. Exercise: receive an import batch of components from start to finish
About 40 minutes. There are no step-by-step images; your company does it and checks the result itself.
- Create a purchase order for the vendor
Tianjin Huaxinin CNY, one lineLK0188(Front Disc Rim 2.15x10 Vepas, V6) quantity 20. Confirm it. - Receive the goods at the customs clearance area. Create the freight forwarder's bill for one Port Customs, Handling and Storage Fees line of 500,000. Create the customs clearance request, in Extra Expenses choose the customs fee line of that bill, click Allocate Expenses, Open, Confirmed by Custom.
- Receive the goods into the warehouse and store them. Create the vendor bill.
- Check: do the landed cost documents of the batch add up to the duty plus 500,000? In Valuation, does the total added value of
LK0188equal exactly that figure? Does the bill appear in Aged Payable? - Answer for yourself: why is it blocked if you choose By Quantity on a batch with several units of measure?