Viindoo demo handbook for manufacturing and assembly

Part XI. Approvals

This part answers these questions: which jobs in the workshop need a person with the authority to sign, who approves, from what level an approval is required, and whether the workshop is stopped if nothing is approved yet. The readers are the business owner, the production manager, the purchasing manager and the people who must submit requests.

Approval in Viindoo is a separate app. Each business process (bill of materials, engineering change order, procurement request, purchase order, subcontracting, maintenance, payment and so on) has its own approval type that declares who approves and in which sequence. A person who needs approval submits an approval request; the request goes through the statuses Draft, To Approve, Approved, Done (or Refused, Cancelled).

Lesson 75. Approval configuration: which types are on, who approves, what thresholds

About 20 minutes. By the end of this lesson your company knows which approval types are on for the company, who approves each type and under what conditions it applies, and can read a particular approval type. This lesson is read-only; nothing is created.

Step 1 - See the approval groups that are switched on

Go to Approval > Configuration > Settings.

PathApproval > Configuration > Settings
Approval settings

What you should see: the group Approvals and the group Integration with the boxes labelled OmniApproval™: Flexible Approval Flow is ticked, Purpose-Based Approvals is not ticked; most boxes in the integration group are ticked (see the table below).

Approval group (label on screen) State What is lost if it is off
OmniApproval™ - Flexible Approval Flow On There is no approval base, and none of the groups below can be used
OmniApproval™ - MRP Approvals On Bills of materials and manufacturing orders have no Get Approved button
OmniApproval™ - ECO Approvals On Engineering change orders do not go through approval
OmniApproval™ - Procurement Approvals On There is no procurement request waiting for approval before a supply method is chosen
OmniApproval™ - Purchase Approvals On There is no purchase request and no approval of purchase orders in the approval style
OmniApproval™ - Stock Approvals On Delivery orders and warehouse transfers do not go through approval
OmniApproval™ - MRP Subcontracting Approvals On Subcontracting requests do not go through approval
OmniApproval™ - Maintenance Approvals On Maintenance requests do not go through approval
OmniApproval™ - Accounting Approvals, Quote & Order Approvals, Employee Contract Approvals, Employee Advance Management, Project & Task Approvals, Overtime Approvals, Recruitment Approvals, Estimate Approvals On The matching business process has no approval type
OmniApproval™ - Purpose-Based Approvals, Timesheet Approvals, Product Approval, Partner Approval Off Not used at present

Step 2 - See the list of approval types

Go to Approval > Configuration > Approval Types.

PathApproval > Configuration > Approval Types
List of approval types

What you should see: 23 types, each line with Title, Code, Type and three counts of requests (all, approved, waiting); on the left there are the filter groups Company and Applies To (by the business process the type applies to).

The manufacturing-related types that are on for Công ty Cổ phần SX Viindoo. The approver names are sample data:

Approval type What it approves Who approves Conditions, thresholds
Bill of Materials A new or edited bill of materials Phạm Thu Trang or Phạm Thị Thu Hương (declared together in one step) Sent from Actions > Get Approved of the bill of materials; requires the employee to have a manager
Engineering Change Order Engineering change orders (ECO) Phạm Thu Trang Sent from Actions of the change order; requires a manager
Procurement A procurement request for one or more products; after approval the system chooses the suitable supply method Phạm Thu Trang Created only from the Approval screen; requires a manager
Purchase Request A purchase request Lê Văn Hậu or Phạm Thu Trang Created only from the Approval screen; does not require a manager
Component Purchase Order over 500 Million A purchase order Step 1 Trần Thị Hạnh, step 2 Nguyễn Văn Quang, in sequence Company Total (converted to VND, including foreign-currency orders) from 500,000,000 VND and the order in the status RFQ, RFQ Sent or To Approve
Subcontracting Request An outside subcontracting request Phạm Thu Trang or Phạm Thị Thu Hương Created only from a subcontracting request
Assembly Material Issue Approval A confirmed manufacturing order Phạm Thị Thu Hương Sent from Actions of the manufacturing order; does not require a manager
Delivery Orders Delivery orders that are not yet finished Phạm Thu Trang or Phạm Thị Thu Hương Only for delivery orders in the status draft, waiting, confirmed or ready
Inventory Reallocation Transfers between warehouses Phạm Thu Trang or Phạm Thị Thu Hương Created only from the Approval screen
Maintenance A maintenance request The seven people declared (Lê Văn Hậu, Nguyễn Thị Hà My, Phạm Thu Trang, Phạm Thị Thu Hương, Trần Thị Ngọc Ánh, Vũ Văn Tài, Đỗ Văn Kiên) No extra condition
Payment Request A general request Đặng Quốc Bảo, then Lê Thị Hồng Nhung, then Hoàng Minh Khôi (three steps) In sequence, all three approvals
General A general request Phạm Thu Trang Created only from the Approval screen

The following types are off for this company: Production Order (a type of its own), Purchase Order (the standard type), Vendor Payments, Customer Refunds, Customer Invoice and Coaching. The type Quotation is on, with one request waiting. So for a manufacturing order the type in use is Assembly Material Issue Approval, and it can be sent only when the order has been confirmed (see the lesson Does approval block confirming a manufacturing order?).

Step 3 - Open the type Bill of Materials

Click the line Bill of Materials.

PathApproval > Configuration > Approval Types > Bill of Materials
Approval type Bill of Materials

What you should see: the smart buttons To-approve Requests, Approved Requests and Requests, and three report buttons (Requests Overview, Approval Analysis, Approver Workload). The tabs are Approval Process, Fields Enablement, Enable Approvals for Models, Defaults / Auto-fill and Inline Hooks / Process Automation. The Approval Process tab has Manager Approval set to Required, Sequential Approvals ticked, Approve by Any in Step ticked, Days to Approve 1 and Minimum Approvals 2; the section Extra Approval Steps lists a step Specific Approvers with two approver names. On the trial request of the bill of materials, the system assigned only Phạm Thu Trang and recorded the minimum approvals as 1, so the request could go on.

Step 4 - Open the type Component Purchase Order

Click the line Component Purchase Order over 500 Million.

PathApproval > Configuration > Approval Types > Component Purchase Order over 500 Million
Approval type Component Purchase Order

What you should see: Type is Quotation / Purchase Order, Manager Approval is None, Sequential Approvals is ticked, Approve by Any in Step is not ticked, Minimum Approvals 2, two Specific Approvers steps: Trần Thị Hạnh then Nguyễn Văn Quang, both Required.

Step 5 - Read the condition of application

Click the tab Enable Approvals for Models and scroll down to the section Condition Domain.

PathApproval > Configuration > Approval Types > Component Purchase Order over 500 Million > Enable Approvals for Models tab
Condition of application of the type Component Purchase Order

What you should see: Applies To Purchase Order and Field Mapping Strategy One record per approval request; under Condition Domain, Applicable Records Domain reads Match all of the following rules: Status is in RFQ, RFQ Sent, To Approve, and Company Total >= 500,000,000.00. Company Total (the amount converted to VND) is used instead of Total so that a purchase order in Chinese yuan or US dollars is compared with the right threshold; the section Before-Approval Required Domain is Match all records, which means no condition has to be met before sending for approval. Approving purchase orders in the standard purchasing way (two levels by amount) is off; the approval threshold of purchase orders of the company comes from this approval type.

Lesson 76. Submitting and approving an approval request

About 15 minutes. By the end of this lesson your company takes the approval request of the bill of materials Zeta Electric Vehicle (created in the lesson Submitting a bill of materials for approval) from Draft to Done, and knows what each button does in each status.

If you do not have a request yet, do the lesson Submitting a bill of materials for approval first.

Step 1 - Open the request screen

Go to Approval > Approval Request > Request.

PathApproval > Approval Request > Request
Approval request screen as columns

What you should see: the requests are arranged in columns by status: Draft, To Approve, Approved, Done, Refused, Cancelled (with a count on each column; in the picture Draft 8, To Approve 6, Approved 8, Done 3); each card shows the number, the title, the type, the request date, the approval progress bar and the deadline.

Step 2 - Find your own request

Type Zeta Electric Vehicle in the search box and press Enter.

PathApproval > Approval Request > Request
Filtering requests by name

What you should see: only the cards whose name contains Zeta remain: the card of your bill of materials request (in the picture one in Approved and one, circled, in Done) and the cards of the engineering change orders in the Done column.

Step 3 - Open the request and see the approvers

Click the card, then click the tab Approvers.

PathApproval > Approval Request > Request > [APVL...] Bill of Materials for Zeta Electric Vehicle
Approvers tab of the request

What you should see: one approver line (Phạm Thu Trang) with the Required box ticked, in a table with the columns Responsible (Multi), Required, Status, Date and Extra Badge (in the picture the request is already finished, so the status reads Approved with the time); a request in Draft has the Submit button at the top left. The yellow warning at the top is about the approver set-up, for example No manager of this employee is a Team Approver; Phạm Thu Trang approves instead. An Approval administrator can add the manager to Team Approver. (or Approval request is invalid due to missing required information: Employee linked to the requester... when the account has no employee record); the request can still be submitted.

Step 4 - Submit the request

Click Submit.

PathApproval > Approval Request > Request > [APVL...] Bill of Materials for Zeta Electric Vehicle
Request in the status To Approve

What you should see: the status is To Approve; Next Approver(s) lists the approvers (Lê Văn Hậu and Phạm Thu Trang in the picture); the status of the approver line is To Approve; the buttons Refuse and Cancel appear, together with Approve for an approver (Force Approval in the picture, because the logged-in account is not an approver). In the chatter, Planned Activities lists an Approve to-do for each approver, due by the approval deadline (1 day).

Step 5 - Approve

The approver clicks Approve.

PathApproval > Approval Request > Request > [APVL...] Bill of Materials for Zeta Electric Vehicle
Approved request

What you should see: the status is Approved, Approval Progress is 100%, Approved Date has a date and time, and the approver line changes to Approved with the time. The buttons Refuse, Mark as Done (circled), Cancel and the button to view the source record appear.

Step 6 - Mark as done

Click Mark as Done to close the request.

PathApproval > Approval Request > Request > [APVL...] Bill of Materials for Zeta Electric Vehicle
Request done

What you should see: the status is Done; the chatter records each step: Draft → To Approve, the approver's approval note, To Approve → Approved, Approved → Done. What remains is the button Cancel and the button View Bill of Materials, to go back to the original bill of materials.

The table of buttons by status:

Status Buttons that can be clicked Result
Draft Submit Goes to To Approve, and the approver receives a to-do
To Approve Approve Goes to Approved once enough approvals are given
To Approve Refuse Goes to Refused
To Approve Cancel Goes to Cancelled
Approved Mark as Done Goes to Done; for the request of an engineering change order, this is the moment the change is applied to the order (see the lesson Engineering change orders (PLM))

When the logged-in account is not in the approver list of the request, the button Force Approval appears instead of Approve (see the lesson Does approval block confirming a manufacturing order?).

Lesson 77. Does approval block confirming a manufacturing order?

About 20 minutes. This lesson answers, with a real run, a common question: if the approval request of a manufacturing order is not approved yet, is the workshop stopped? The conclusion is at the end of the lesson.

Step 1 - Open a confirmed order and open Actions

Open a manufacturing order in the status Confirmed (for example the order for one Zeta Electric Vehicle (Matte black) in the lesson Engineering change orders (PLM)). Click the gear icon Actions next to the order number.

PathManufacturing > Operations > Manufacturing Orders > NM1/MO/... > Actions
Actions menu of a confirmed order, line Get Approved

What you should see: the menu has the lines Print, Duplicate, Delete, Move Message Thread, Get Approved (circled), Post WIP Accounting Entry, Split, Lock/Unlock, Scrap, Plan based on Components Availability, Create Subcontracting Request and Mrp: Unplan Production Orders. If the order is still Draft, the Actions menu does not have this line: the order must be confirmed first and then approval can be requested.

Step 2 - Choose Get Approved and create the request

Click Get Approved. In the dialog Submit for Approval, Approval Request Type is Assembly Material Issue Approval. Click Create Approval Request.

PathManufacturing > Operations > Manufacturing Orders > NM1/MO/... > Actions > Get Approved
Submit for Approval dialog of the manufacturing order

What you should see: a blue note says the type is configured with One record per approval request; Approval Request Type is Assembly Material Issue Approval; Source Records lists the manufacturing order (columns Approval Title, Reference, Date, Employee, Manufacturing Order, Source Warehouse, Destination Warehouse).

Step 3 - Read the request just created

PathApproval > Approval Request > Request > [APVL...] Assembly Material Issue Approval for NM1/MO/...
Material issue approval request goes to To Approve by itself

What you should see: the request has a number like [APVL...], Reference is the order number, the request lines are the components of the order, and the request is first in Draft with a Submit button, as in the picture; a request created from an order may also be submitted by the system straight away, and then the status is already To Approve (as in the picture of step 6, request APVL00076), with the buttons Refuse, Cancel, Force Approval and View Manufacturing Order. The approver is Phạm Thị Thu Hương, who is not the logged-in account, so My Approval Status says Not involved.

Step 4 - Go back to the manufacturing order

Click View Manufacturing Order (or open the order again from the Manufacturing menu).

PathManufacturing > Operations > Manufacturing Orders > NM1/MO/...
Manufacturing order with a request waiting for approval

What you should see: at the top right of the order form there is a yellow ribbon WAITING FOR APPROVALS; the chatter says An approval request has been created: [APVL...] Assembly Material Issue Approval for NM1/MO/... from . The request does not change the status of the order.

Step 5 - Click Start while the request is not approved

Click Start on the order.

PathManufacturing > Operations > Manufacturing Orders > NM1/MO/...
The order can still start while the request is not approved

What you should see: the order goes to In Progress (In Progress lights up on the status bar of Draft, Confirmed, In Progress, Done, and the line Confirmed → In Progress is in the chatter) while the ribbon WAITING FOR APPROVALS is still there. No error dialog blocks it.

Step 6 - Try to refuse or cancel the request with an account that is not the approver

Open the request of step 3 again and click Refuse (or Cancel).

PathApproval > Approval Request > Request > [APVL...] Assembly Material Issue Approval for NM1/MO/...
The system reports invalid fields

What you should see: the system does not change the status; it shows a red message Invalid fields: followed by Employee, Source Warehouse and Destination Warehouse, and those three boxes turn red. A request of the type Assembly Material Issue Approval created from an order does not fill in these mandatory boxes, so a request of this kind can be acted on further only when they have values. This is a point your company needs to settle when applying it for real (see the section The figures are assumptions to be confirmed in the Reference and appendices).

Conclusion from this run:

Question Result
Can approval be requested while the order is still Draft No, the line Get Approved appears only after the order is confirmed
Does an unapproved request block Start No block: the order still goes to In Progress, with only the ribbon WAITING FOR APPROVALS as a mark
Is the request of a manufacturing order a gate or a record It is a request-and-tracking mechanism: it records who approves the materials of the order, and does not lock the order by itself
Was Done on the order tried Not yet: clicking Done causes stock receipts and journal entries, so this lesson does not do it; your company can try it on a separate order if needed
For a large purchase order (type Component Purchase Order over 500 Million) Not tried in this lesson; see the part Purchasing and import

Lesson 78. Approval reports

About 15 minutes. The Approval app has five reports. The table lists all of them and each report has one step to open it.

Report What question it answers Path
Overview How many requests per month, in which status Approval > Reports > Overview
Approval Analysis Which request type has the most requests, in which status each type is Approval > Reports > Approval Analysis
Approver Workload How many requests each person holds, who is the bottleneck Approval > Reports > Approver Workload
Approval Flow Logs Who changed the approver, at which step, for what reason Approval > Reports > Approval Flow Logs
Flow Modified Approval Requests Which requests had their approval flow changed midway Approval > Reports > Flow Modified Approval Requests

Step 1 - Open the Overview report

PathApproval > Reports > Overview
Approval overview report

What you should see: the screen Approval Requests Overview: a bar chart by month (September 2026, October 2026, November 2026 in the picture), each bar coloured by status (legend Cancelled, To Approve, Draft, Done, Approved) and a line (Sum) joining the totals; at the top right there are buttons to switch to a pivot table and a list.

Step 2 - Open Approval Analysis

PathApproval > Reports > Approval Analysis
Approval analysis report

What you should see: a bar chart by approval type (Assembly Material Issue Approval, Payment Request, Purchase Request, Bill of Materials, Engineering Change Order, Employee Advance Approval...), coloured by status. The highest bar is the type that has the most requests.

Step 3 - Open Approver Workload

PathApproval > Reports > Approver Workload
Approver workload report

What you should see: each bar is one approver with the number of requests they hold, coloured by status (legend Pending, Approved, Draft). The person with a high bar in the Pending part is the bottleneck.

Step 4 - Open Approval Flow Logs

PathApproval > Reports > Approval Flow Logs
Approval flow logs report

What you should see: a table with the columns Created on, Approval Request, Approval Type, Action, Actor, Target User, Anchor Step, Position and Reason. If nobody has changed an approval flow midway, there are no real rows and the screen only shows faded sample rows; that is a correct result.

Step 5 - Open Flow Modified Approval Requests

PathApproval > Reports > Flow Modified Approval Requests
Flow modified approval requests report

What you should see: a list with the columns Title, Type, Employee, Request Date, Deadline, Activities, Approval Progress, Status, My Approval Status, Flow Modified, Add and Remove; it is empty (the screen shows faded sample rows and Create new document) if no request has had its flow changed.

Lesson 79. Practice exercise: from bill of materials to engineering change order

About 40 minutes. There are no step-by-step pictures.

The task. Your company has finished the model Zeta Electric Vehicle and the bill of materials ZETA-V2 in the part Manufacturing engineering, and wants every change of a bill of materials to carry an approval mark.

What to do.

  1. Send an approval request for the bill of materials ZETA-V2, submit it, approve it, mark it as done.
  2. Make a new engineering change order (apply on Production) that changes any one component in the bill of materials ZETA-V2 and take it to Done.
  3. By reading the configuration, write down: (a) who approves the component purchase order and from which amount; (b) which approval type is used for a manufacturing order and when it can be requested.
  4. Open Approval > Reports > Overview and Approver Workload, and write down the number of requests your company has sent in each status.

Self-check. It is right when: (a) the two requests of tasks 1 and 2 have the status Done and the history in the chatter has all four steps Draft → To Approve → Approved → Done; (b) the manufacturing order of task 2 has changed to the new bill of materials; (c) the answer to task 3: a purchase order is approved in two steps (Trần Thị Hạnh then Nguyễn Văn Quang) when the company total is from 500,000,000 VND; a manufacturing order uses the type Assembly Material Issue Approval, which can be requested only after the order has been confirmed; (d) the report Approver Workload has the name of the approver that your company chose.

If it does not come out like this. You do not see the line Get Approved: check whether the order has been confirmed (for a manufacturing order) or whether the approval app of that process has been switched on (see the table in the lesson Approval configuration: which types are on, who approves, what thresholds). You do not see the button Approve: the logged-in account is not an approver of the request; look at the Approvers tab.