Viindoo demo handbook for manufacturing and assembly
Part XII. Accounting and costing
Lessons in this part
- Lesson 80. Costing accounting and bank configuration
- Lesson 81. Cost of one order when it is completed
- Lesson 82. Post work in progress at the end of the period
- Lesson 83. Allocate production costs to completed orders
- Lesson 84. Production cost report
- Lesson 85. Reconcile the bank statement
- Lesson 86. Value added tax
- Lesson 87. Financial statements B01-DN, B02-DN, B03-DN
- Lesson 88. The general ledger, the trial balance and the books in the Ministry of Finance form
- Lesson 89. Aged receivables and payables
- Lesson 90. Catalog of accounting reports and print templates
- Lesson 91. What the system does not do by itself
- Lesson 92. Self-study exercise - a month of product cost
This part answers these questions: how much does one vehicle or one frame assembly cost; how much is the value of work in progress at the end of the period; how do depreciation and workshop payroll enter the product cost; have the receipts and payments been matched to the bank statement; how much VAT is payable; and how are the financial statements under Circular 99 read. The chief accountant, the cost accountant and the director read this part. The base configuration (company, Circular 99, product categories) is in General configuration.
Lesson 80. Costing accounting and bank configuration
About 10 minutes. By the end of this lesson your company knows where the system takes the hourly rate, the expense account and the work-in-progress account from.
Step 1 - See the manufacturing accounting accounts of the company
Open the accounting settings page and scroll down to the section MRP Accounting.
Accounting > Configuration > Settings
What you should see: Production WIP Account = 154, Production WIP Overhead Account = 627, Default Work Center Expense Account empty, and the box Automatically create accounting entries to work in progress not ticked. The two accounts 154 and 627 are where the period-end work-in-progress entry posts its debit and credit (lesson Post work in progress at the end of the period). If Production WIP Overhead Account is left empty, the labor-hour part of the work-in-progress entry is credited to the production account of the product category, which means Debit 154 / Credit 154: the entry still balances, but the hours already worked are not separated from 627.
Step 2 - See the list of work centers and hourly rates
Open the list of work centers.
Manufacturing > Configuration > Work Centers
What you should see: 12 work centers (the teams of the workshop), the column Cost per hour from 130,000 to 230,000 VND, Capacity, Time Efficiency 100 and OEE Target 90. The hourly rates are assumed figures of the demo system.
Step 3 - Open the work center Tổ khung
Click the line Tổ khung (Frame Team).
Manufacturing > Configuration > Work Centers
What you should see: the block Costing Information: Cost per hour 210,000 VND per workcenter, shown on the production cost report in the column Manufacturing Overhead; Employee Hourly Cost 41,000 VND per employee, shown in the column Direct Labor; Expense Account 627 Manufacturing overhead. How to define a work center, operations and hourly rates is written in full in Manufacturing engineering, lesson Work centers, operations, hourly rates and expense accounts.
Step 4 - See the types of manufacturing cost
Open the list of cost types.
Accounting > Configuration > Management > Classification of Manufacturing Cost
What you should see: two lines, Manufacturing Overhead and Direct Labor. Each cost allocation document and each hourly-rate line chooses one of these two types; the production cost report splits its columns by type.
Step 5 - See the list of taxes
Open the list of taxes.
Accounting > Configuration > Accounting > Taxes
What you should see: 20 taxes, with the columns Tax Type (Purchases, Sales), Label on Invoices and Is VAT: deductible VAT and output VAT at 0%, 5%, 8%, 10% and VAT EXEMPTION; import tax and VAT on imported goods; export tax.
| Configuration | Current setting | What is lost if it is not set |
|---|---|---|
| Expense account of each work center | 627 for all 12 work centers | Labor hours fall on the cost of goods 632 or post Debit 154 / Credit 154 |
| Cost per hour of the work center and of the employee | 130,000 - 230,000 VND/hour; 41,000 VND/hour per employee | The product cost has materials only |
| Production WIP Account (154) | Set | The period-end work-in-progress entry cannot be posted |
| Production WIP Overhead Account (627) | Set | Work-in-progress labor hours post Debit 154 / Credit 154, and 627 at period end does not drop by the hours already worked |
| Classification of Manufacturing Cost | Two types | The production cost report does not split direct labor from overhead |
| Bank journal (account 1122, suspense accounts 1131, 1132) | Exists, with 38 monthly statements from 09/2023 to 10/2026 | Reconciliation is not possible |
Lesson 81. Cost of one order when it is completed
About 15 minutes. By the end of this lesson your company has made a manufacturing order for one powder-coated frame assembly Nova, seen that the cost is made of materials and labor hours, and can read the three places where the cost is shown. The lesson takes the shortest path for the accountant (it does not use the shop floor screen); the full way of working at the workshop, with a finished vehicle, the frame number and the quality check, is in Shop floor production.
Step 1 - Create a new manufacturing order
Open the list of manufacturing orders and click New.
Manufacturing > Operations > Manufacturing Orders
What you should see: a new order form in the status Draft.
Step 2 - Choose the product and confirm
In the Product box type BTP-KHUNG-NOVA and choose [BTP-KHUNG-NOVA] Powder-coated frame assembly - Nova, keep Quantity at 1, and click Confirm.
Manufacturing > Operations > Manufacturing Orders
What you should see: before you click, the tab Components fills in 7 components by itself from the bill of materials (Mira Motorbike Frame, Center Shaft, A-Leg Mira, Side Stand Mira, 2 Rear Shock Absorber, Complete Bolt and Screw Set for One Vehicle, 0.63 kg of powder coating), taken from NM1/Trước sản xuất (NM1/Pre-production).
Step 3 - Read the confirmed order
After you click Confirm, read the order again.
Manufacturing > Operations > Manufacturing Orders
What you should see: the order has a number (NM1/MO/01278 in the trial run), the status Confirmed, Quantity 0.00 / 1.00, Component Status = Available, the smart buttons ECO, Transfers 1, Overview and Overview Progress, and the buttons Produce All, Plan, Start, Cancel, Quality Alert and Maintenance Request. The warehouse is set up in two steps: components must be picked from Kho Tổng (Main Warehouse) to the area before production before assembly.
Step 4 - Open the component picking
Click the smart button Transfers.
Manufacturing > Operations > Manufacturing Orders
What you should see: the component picking (NM1/PC/01545 in the trial run) in the status Ready, with the status bar Draft > Waiting > Ready > Done, Operation Type "Nhà máy Yên Mỹ: Pick Components" (Yen My Factory: Pick Components), Source Location NM1/Tồn kho (NM1/Stock) and Destination Location NM1/Trước sản xuất (NM1/Pre-production), Source Document the order number, and the 7 component lines. The Quantity column shows what is reserved; a component that is short in stock shows less than its Demand (for example the Rear Shock Absorber), and the button Check Availability is offered next to Validate.
Step 5 - Validate the component picking
Click Validate on the picking.
Manufacturing > Operations > Manufacturing Orders
What you should see: the button Validate is circled. If a message offers to create a backorder, choose No Backorder; the dialog that opens next asks for the Transfer Date, which defaults to the moment you click.
Step 6 - Keep the date and confirm
Keep the date and click Validate in the dialog.
Manufacturing > Operations > Manufacturing Orders
What you should see: the dialog closes. Changing the Transfer Date here is how to record a stock transfer that took place the day before.
Step 7 - Check that the picking is done
Read the status of the picking again.
Manufacturing > Operations > Manufacturing Orders
What you should see: the status Done. This picking only moves the components between stock locations; it creates no journal entry yet.
Step 8 - Produce all
Go back to the order (if it shows a warning activity about the picking, mark it as done) and click Produce All.
Manufacturing > Operations > Manufacturing Orders
What you should see: the Quantity column of the 7 components is filled in (in green: 0.63, 1.00, 1.00, 1.00, 2.00, 1.00, 1.00); clicking the button opens a dialog with the box Date Done.
Step 9 - Confirm the completion date
Keep the date and click Validate.
Manufacturing > Operations > Manufacturing Orders
What you should see: the order changes to Done.
Step 10 - Read the completed order
Read the order again.
Manufacturing > Operations > Manufacturing Orders
What you should see: the status Done, Progress 100 %, the column Consumed ticked on all 7 lines; the smart button bar now also has Traceability, Loss Components Analysis, Loss By-products Analysis, Product Moves, Overview and More. Nobody has timed the operation "Hàn hoàn thiện, sơn tĩnh điện khung" (finish welding and powder coating of the frame), so the system takes the expected duration of 30 minutes as the real time.
Step 11 - Open the cost analysis
Click More and choose Cost Analysis.
Manufacturing > Operations > Manufacturing Orders
What you should see: the menu More has Cost Analysis, Journal Entries (9), Overview Progress and Quality Checks. Cost Analysis opens only when the order is done.
Step 12 - Read the cost by cost item
Read the Production Cost Analysis screen.
Manufacturing > Operations > Manufacturing Orders
What you should see: at the top Total Quantity 1.00 Units, from 1 manufacturing order, Total Cost 1,093,300 VND and Unit Cost 1,093,300 VND. The block Direct Materials Costs has each component with Standard Quantity, Actual Consumption Quantity, Unit Cost and Total Cost: a total of 967,800 VND.
Step 13 - Read the labor hours on the cost analysis
Scroll down to the last two blocks.
Manufacturing > Operations > Manufacturing Orders
What you should see: Direct Labor 20,500 VND and Manufacturing Overhead 105,000 VND, both on the line "Hàn hoàn thiện, sơn tĩnh điện khung".
| Cost item | How it is calculated | Trial order |
|---|---|---|
| Direct materials | Quantity actually consumed x the average price of the component | 967,800 VND |
| Manufacturing overhead (machine hours) | 0.5 hour x 210,000 VND (cost per hour of Tổ khung) | 105,000 VND |
| Direct labor | 0.5 hour x 41,000 VND (employee hourly rate of Tổ khung) | 20,500 VND |
| Cost received into stock | 1,093,300 VND |
Step 14 - See the journal entries of the order
Go back to the order, click More and choose Journal Entries.
Manufacturing > Operations > Manufacturing Orders
What you should see: 9 entries in the journal Inventory Valuation, Posted: 7 component entries (Debit 154 / Credit 152, total 967,800 VND), "NM1/MO/01220 - Cụm khung sơn tĩnh điện Nova" (the Nova powder-coated frame assembly) 1,093,300 VND (Debit 155 / Credit 154) and "NM1/MO/01220 - Nhân công" (labor) 125,500 VND (Debit 154 / Credit 627). The account 154 of the order returns to 0.
Step 15 - Compare with the manufacturing order overview
Go back to the order and click the smart button Overview.
Manufacturing > Operations > Manufacturing Orders
What you should see: the MO Overview screen with the columns Quantity, Unit Cost and Real Cost: on the first line Unit Cost is 1,093,300 VND but Real Cost is 1,072,800 VND; the line Operations shows 0.5 hours x 210,000 VND = 105,000 VND; at the bottom Total Cost of Components 967,800 VND and Total Cost of Operations 105,000 VND.
The three places where the cost is shown, and why the figures differ:
| Screen | Figure of the trial order | What it calculates |
|---|---|---|
| Cost Analysis | 1,093,300 VND | Materials + machine hours + labor hours; exactly the value received into stock |
| The entry that receives the finished goods (Debit 155) | 1,093,300 VND | The figure the accountant uses; the cost of goods at sale is taken from it through the average price |
| Overview of the manufacturing order, column Real Cost | 1,072,800 VND | Materials + machine hours; it does not add labor hours (20,500 VND) |
The accountant reconciles against Cost Analysis and the entry; the order Overview is for a quick comparison with the standard cost.
Lesson 82. Post work in progress at the end of the period
About 10 minutes. By the end of this lesson your company has left one order unfinished and posted the work-in-progress entry at the end of the month for that order. The work-in-progress entry brings the value of the components already taken and the labor hours already worked on unfinished orders into 154 on the last day of the period, then reverses itself on the first day of the next period, so that B01-DN at month end shows the work in progress correctly.
Step 1 - Create and confirm a new order, pick the components
Repeat Step 1 to Step 7 of the lesson Cost of one order when it is completed with one Nova frame assembly: create the order, Confirm, open Transfers, Validate the component picking. Stop there and do not click Produce All.
Manufacturing > Operations > Manufacturing Orders
What you should see: the new order (NM1/MO/01289 in the trial run) in Confirmed, Component Status Available, Quantity 0.00 / 1.00.
Step 2 - Record the hours already worked on the operation
Open the tab Work Orders, click the Real Duration box of the line "Hàn hoàn thiện, sơn tĩnh điện khung", type 15:00 and click the save icon.
Manufacturing > Operations > Manufacturing Orders
What you should see: before you save, the operation line has the status Ready, Expected Duration 30:00 and Real Duration 15:00; after you save, the status of the operation and of the order changes to In Progress. At the workshop the team leader records the hours with the start and pause buttons on the Shop Floor screen (Shop floor production); typing them here is how the accountant or the workshop manager adds hours.
Step 3 - Mark the components as taken into assembly
Open the tab Components and tick the box Consumed on all 7 lines.
Manufacturing > Operations > Manufacturing Orders
What you should see: the 7 boxes Consumed are ticked. Only components marked as consumed are counted in the value of work in progress; a component just moved to the area before production and not yet fitted is still stock.
Step 4 - Read the order in progress
Read the top of the order again.
Manufacturing > Operations > Manufacturing Orders
What you should see: the status bar on In Progress, Progress 0 % (no finished product yet), Quantity 0.00 / 1.00; the operation line shows Expected Duration 30:00 and Real Duration 15:00.
Step 5 - Open the work-in-progress function
Click the gear icon next to the order number and choose Post WIP Accounting Entry. (To post for several orders at once: on the list of orders, tick the orders In Progress, click Actions > Post WIP Accounting Entry.)
Manufacturing > Operations > Manufacturing Orders
What you should see: the menu has the line Post WIP Accounting Entry.
Step 6 - Choose the period-end date and the reversal date, and post
In the dialog, Date is the posting date and Reversal Date the day the entry reverses itself (the trial run uses 11/23/2026 and 11/24/2026; for a real month end, set the last day of the month and the first day of the next month). Read the lines and click Post WIP (the other button is Discard).
Manufacturing > Operations > Manufacturing Orders
What you should see: Journal Inventory Valuation, Reference "Manufacturing WIP - NM1/MO/01289", Date 11/23/2026, Reversal Date 11/24/2026, and three lines that the system proposes by itself: Credit 152 Raw materials 971,340 VND (label "WIP - Component Value", the value of the consumed components), Credit 627 Manufacturing overhead 62,750 VND (label "WIP - Overhead": 15 minutes x (210,000 + 41,000) VND/hour), Debit 154 Work in progress 1,034,090 VND. The accountant can edit the lines before posting; the entry must balance to be posted, and the reversal date must be after the posting date.
Step 7 - Read the work-in-progress entry
Open the entry you just created.
Accounting > Accounting > Journal Entries
What you should see: a posted three-line entry of the same kind (the screenshot shows an example entry, STJ/2026/10/0902, of an earlier order: Credit 152 967,800 VND, Credit 627 62,750 VND, Debit 154 1,030,550 VND, Accounting Date 10/31/2026), status Posted, with the tabs Journal Items, Other Info and Counterparts Mapping, the buttons Reverse Entry, Reset to Draft and Remove Counterparts, and the smart button Manufacturing 1. The reversing entry is created with the entry and is dated on the reversal date. If the posting date is still in the future, the entry stays in Draft and posts itself on its accounting date.
The effect of one work-in-progress posting:
| Place | Change |
|---|---|
| Stock | No change: the components stay in the area before production until the order is completed |
| Accounting on the last day of the period | 154 goes up, 152 and 627 go down by exactly the part that has been done |
| Accounting on the first day of the next period | The reversing entry puts 154, 152, 627 back as before; when the order is completed, the completion entry posts in full |
| Reports | B01-DN on the last day of the period shows the work-in-progress value in the line Inventories |
Lesson 83. Allocate production costs to completed orders
About 15 minutes. By the end of this lesson your company has brought the depreciation of the assembly line for September into the cost of the Aura vehicles made in September. The cost at the completion of an order has only materials and labor hours at the hourly rate; the other real costs of the workshop (machine depreciation, the difference between actual payroll and the labor hours already counted, electricity) are brought in by the accountant with a Production Cost Allocation document. The lesson chooses depreciation because this item is not yet in the cost: the labor hours at order completion were already credited to 627 at the hourly rate, so allocating payroll 622 in full would count the labor hours twice; the depreciation of the line is in no hourly rate, so allocating all of it is correct. For payroll, the accountant allocates only the difference between actual payroll and the labor hours already counted.
Step 1 - Create a new allocation document
Open the list of documents and click New.
Accounting > Accounting > Production Cost Allocation
What you should see: a new Landed Cost form, status Draft, with the boxes Date, Apply On, Journal (Inventory Valuation) and the tab Additional Costs.
Step 2 - Choose the orders that receive the cost
Set Date to 09/30/2026 (the date format on screen is month/day/year), set Apply On to Manufacturing Orders. Click the Manufacturing order box and choose Search More...; in the search box type Aura and choose the option that searches the product, click the column title Start twice to put the newest on top, tick the Aura vehicle orders that started in September 2026 (hover over the date box to see the exact date), and click Select.
Accounting > Accounting > Production Cost Allocation
What you should see: the box Search: Manufacturing order lists only done orders; the trial run ticks 16 orders (NM1/MO/01176-001 to -007, NM1/MO/01177, NM1/MO/01182, NM1/MO/01184-001 to -004, NM1/MO/01185-001 to -003).
Step 3 - Choose the cost type
Accounting > Accounting > Production Cost AllocationIn the box Type of Manufacturing Cost choose Manufacturing Overhead.
Accounting > Accounting > Production Cost Allocation
What you should see: Date 09/30/2026, Apply On = Manufacturing Orders, 16 orders in the box Manufacturing order, Type of Manufacturing Cost = Manufacturing Overhead. The cost type box appears only after the orders have been chosen.
Step 4 - Choose the depreciation entry to allocate
In the tab Additional Costs, click Add a line. In the box Related Cost Journal Items type ASSET/2026/09/0003 and choose the line that ends with [Debit 6274]. In the box Product type Allocated Manufacturing Overhead: the dropdown shows the existing product on top, followed by Create "Allocated Manufacturing Overhead", Search More... and Create and edit...; choose the existing product.
Accounting > Accounting > Production Cost Allocation
What you should see: the box Account fills in 6274 Depreciation expense by itself, and the box Cost fills in 1,666,667 VND (the September depreciation of the asset on the journal item ASSET/2026/09/0003). The list of journal items shows only amounts not yet fully allocated; an item already fully allocated does not show again. If the line ASSET/2026/09/0003 is no longer there, choose another 6274 depreciation item that is still on the list.
Step 5 - Choose how to split
In the box Split Method choose By Quantity, leave the line's Type of Manufacturing Cost at Manufacturing Overhead, and click the save icon.
Accounting > Accounting > Production Cost Allocation
What you should see: the line has the boxes Related Cost Journal Item, Product, Description, Account 6274, Split Method By Quantity, Type of Manufacturing Cost Manufacturing Overhead and Cost 1,666,667 VND; the document shows Date 09/30/2026, Apply On Manufacturing Orders, the 16 orders and the type Manufacturing Overhead. The other split methods are Equal, By Current Cost, By Weight and By Volume.
Step 6 - Compute and read the split
Click Compute and open the tab Valuation Adjustments.
Accounting > Accounting > Production Cost Allocation
What you should see: one line per order, with the columns Cost Line, Production, Related Cost Journal Item, Product, Quantity, Original Value, New Value and Additional Landed Cost. In the posted example LC/2026/0604 shown in the screenshot each vehicle line reads Original Value 10,320,417 VND, New Value 10,763,125 VND, Additional Landed Cost 442,708 VND (7,083,333 VND split equally over 16 vehicles).
Step 7 - Validate the document
Click Validate.
Accounting > Accounting > Production Cost Allocation
What you should see: the Validate and Cancel buttons at the top left, and the document is still Draft (status bar Draft > Posted).
Step 8 - Read the posted document
Read the document again.
Accounting > Accounting > Production Cost Allocation
What you should see: the document has a number (LC/2026/0604 in the posted example), the status Posted, the smart button Valuation, and the field Journal Entry that links to the entry it created. The entry (STJ/2026/09/2634, dated 30/09/2026 in the example): Debit 155 7,083,333 VND / Credit 6274 7,083,333 VND; then, because 15 of the 16 vehicles have been delivered to customers, Debit 632 / Credit 155 6,640,625 VND. The result: 6,640,625 VND goes into the cost of goods of the vehicles already sold, and 442,708 VND stays in the value of the vehicle still in stock.
What the allocation document checks and does not do:
| Point | What the system does |
|---|---|
| Compute is required before Validate | Checked |
| One journal item cannot be chosen twice on the same document; the line must have the same account as the journal item | Checked |
| Automatically choose the 621, 622, 627 items at period end, and calculate the difference between actual payroll and the labor hours already counted | Not done: the accountant chooses the journal item and the amount to allocate |
| Automatically close 621, 622, 627 at period end | No automatic closing entry; this document brings the allocable part into the product cost, and the accountant closes the rest to 632 |
Lesson 84. Production cost report
About 10 minutes. By the end of this lesson your company reads the cost per product and per month, split into three cost items, and sees the depreciation just allocated inside the cost of the Aura vehicles.
Step 1 - Open the production cost report
Open the report.
Accounting > Reporting > Manufacturing Reports > Production Cost Report > Manufacturing > Reporting > Production Cost Report
What you should see: the current month by default; one line per product with the columns Direct Material, Direct Labor, Manufacturing Overhead, Extra Costs, Total Cost, Total Quantity and Unit Cost; the Export XLSX button and Comparison with the previous period. The Nova frame-assembly order of the previous lesson is in the line [BTP-KHUNG-NOVA].
Step 2 - Switch to last month
Accounting > Reporting > Manufacturing Reports > Production Cost ReportClick the period box (it shows the current month) and, in the section Custom, enter Start Date 09/01/2026 and End Date 09/30/2026, then click Apply.
Accounting > Reporting > Manufacturing Reports > Production Cost Report
What you should see: the list of periods: This Month, This Quarter, This Financial Year, Last Month, Last Quarter, Last Financial Year, and the section Custom with Start Date, End Date and the button Apply. (You can also choose Last Month if the previous month is the one you want.)
Step 3 - Find the Aura vehicle line
Read the line [XMD-AURA-DN-TC] Viindoo Aura Electric Motorbike (Matte black, Standard).
Accounting > Reporting > Manufacturing Reports > Production Cost Report
What you should see: the period box reads "From 09/01/2026 to 09/30/2026"; the line Aura Matte black Standard has 7 vehicles, Total Cost 75,455,958 VND and Unit Cost 10,779,423 VND (including the allocated depreciation); the Aura Standard vehicles in Moss green and Burgundy come to 10,763,125 VND each.
Step 4 - Open the detail of one product
Accounting > Reporting > Manufacturing Reports > Production Cost ReportClick the product name on that line.
Accounting > Reporting > Manufacturing Reports > Production Cost Report
What you should see: the Production Cost Analysis screen of the product: Total Quantity 7.00 Units, from 7 manufacturing orders, Total Cost 75,455,958 VND and Unit Cost 10,779,423 VND; a chart of the unit cost of each order; the block Direct Materials Costs lists every component of every order with Standard Quantity and Actual Consumption Quantity so you can see the deviation from the standard; the top of the screen shows Total Quantity, Total Cost and Unit Cost.
Step 5 - Find the depreciation you just allocated
Scroll down to the block of manufacturing overhead.
Accounting > Reporting > Manufacturing Reports > Production Cost Report
What you should see: besides the machine hours of the three assembly operations (columns Cost Name, Manufacturing Orders, Cost Share (%), Cost), each order has a line Allocated Manufacturing Overhead of 442,708 VND; the block total is 5,006,789 VND.
Lesson 85. Reconcile the bank statement
About 15 minutes. By the end of this lesson your company has recorded a customer's bank transfer, entered the matching bank transaction line, and reconciled the two. The bank journal of the company already has 38 monthly statements (09/2023 - 10/2026) reconciled; the lesson adds one new transaction of your company's own.
Step 1 - Create a new receipt
Open the list of customer payments and click New.
Accounting > Customers > Payments
What you should see: the Customer Payments form, status Draft, Payment Type = Receive, and the button Confirm.
Step 2 - Fill in the receipt
Choose Customer "Công ty TNHH Xe điện Hòa Bình", Amount 15,000,000, Memo "Hòa Bình chuyển khoản đặt cọc lô xe tháng 11" (Hòa Bình bank transfer, deposit for the November vehicle batch), Journal Bank, and click Confirm.
Accounting > Customers > Payments
What you should see: Date is today, Payment Method "Manual Payment", and the note "You can add other destination accounts into Payment Details if you don't find it on Destination Account field."
Step 3 - Read the confirmed receipt
Read the receipt again.
Accounting > Customers > Payments
What you should see: a document number (PBNK1/2026/00980 in the trial run), the status In Process (status bar Draft > In Process > Paid), the smart buttons Transaction and Journal Entry, and the button Reconcile until the receipt is matched. The entry: Debit 1131 Receipts in Transit - Unreconciled / Credit 131. The money does not reach 1122 until it is matched to the statement.
Step 4 - Open the bank reconciliation screen
Open the accounting Dashboard, on the Bank card click Transactions.
Accounting > Dashboard
What you should see: the Bank card has a Balance line (the bank journal balance), a Latest Statement line (the balance of the latest bank statement), a Payments line when there are receipts and payments not yet reconciled (including the one you just created), and the buttons Bank Setup, Transactions and Import Statement.
Step 5 - Add a bank transaction line
On the Bank Reconciliation screen, click New.
Accounting > Dashboard
What you should see: the left column holds the bank transactions, and a matched transaction has the label Reconciled; the right column holds the journal entry of the chosen transaction. Every day the accountant uses Import Statement to load a CSV or XLSX statement file instead of typing; the lesson types one line to keep it short.
Step 6 - Fill in the transaction and save
In the Add a Transaction dialog: Date today, Label "Hòa Bình chuyển khoản đặt cọc lô xe tháng 11" (Hòa Bình bank transfer, deposit for the November vehicle batch), Partner "Công ty TNHH Xe điện Hòa Bình", Amount 15,000,000, and click Save.
Accounting > Dashboard
What you should see: Journal Bank, and the box Statement may be left empty (the line can be attached to next month's statement).
Step 7 - Open the transaction you just added
Click the transaction card at the top of the left column.
Accounting > Dashboard
What you should see: the 15,000,000 VND transaction dated today at the top of the list, with only the button Journal Entry and without the label Reconciled; the other lines of the list carry the green Reconciled label.
Step 8 - Accept the suggested match and validate
Read the line the system suggests in the right column and click VALIDATE.
Accounting > Dashboard
What you should see: the system finds the receipt of the same partner and the same amount and proposes: Debit 1122 Bank 15,000,000 VND / Credit 1131 Receipts in Transit - Unreconciled, label "Manual Payment: Hòa Bình chuyển khoản đặt cọc lô xe tháng 11", 15,000,000 VND. The top buttons are VALIDATE and TO CHECK, followed by the model buttons Create Bill and Internal Transfers. Below, the tab Match Existing Entries lists the open receivables of the same partner (filters Partner and Debit items, each with a VIEW button) in case you need to match against an invoice instead of the receipt; the other tabs are Manual Operations and Discuss.
Step 9 - Check the reconciled transaction
Read the transaction again.
Accounting > Dashboard
What you should see: the label Reconciled on the line, and the top button changes to REVERT RECONCILIATION (shown here on a line that was reconciled earlier).
Step 10 - Check the receipt and the print template
Open the PBNK1 receipt again, click the gear icon > Print.
Accounting > Customers > Payments
What you should see: the status Paid; the menu Print has Payment Receipt and Payment Receipt (Template 01-TT/02-TT) in the form of the Ministry of Finance.
The effect of reconciliation:
| Place | Before reconciliation | After reconciliation |
|---|---|---|
| Accounts | Debit 1131 / Credit 131 | Adds Debit 1122 / Credit 1131: 1131 returns to 0 for this item |
| The receipt | In Process | Paid |
| Dashboard | The Payments line of the Bank card includes this item | This item leaves the Payments line; Balance goes up by 15,000,000 VND; Latest Statement goes up only when the transaction is attached to a statement |
| Aged receivable | The 15,000,000 VND is a payment not yet matched to an invoice | No change: the advance waits to be offset against a later invoice |
| B03-DN | No cash flow line yet | The cash received from customers goes up |
Lesson 86. Value added tax
About 10 minutes. By the end of this lesson your company reads the input and output VAT of the period and exports the invoice list.
Step 1 - Open the tax report
Open the report.
Accounting > Reporting > Statement Reports > Tax Report
What you should see: the report Tax Report (VN) from the start of the year to today; the block Purchase of Goods and Services (input VAT at 0%, 5%, 8%, 10%; VAT on imported goods; import tax) and the block Sales of Goods and Services, each line with a Base Amount (the taxable value) and a Balance (the tax amount). Click the period box to choose the month or quarter to declare; PDF and XLSX export.
Step 2 - Open the list of sales invoices
Open the list.
Accounting > Reporting > Invoice Lists > Sales Invoice List
What you should see: the dialog for the list of invoices and documents of goods and services sold (01 -1/GTGT): choose Types Month or Quarter, choose the month, click Print Excel. The purchase list (01 - 2/GTGT) is on the menu line just below, Purchase Invoice List.
On the demo system the deductible VAT is offset every month with an entry "Khấu trừ thuế GTGT tháng ..." (VAT offset for the month ...) (Debit 33311 / Credit 1331) posted by the accountant; the system does not create the offset entry by itself.
Lesson 87. Financial statements B01-DN, B02-DN, B03-DN
About 15 minutes. By the end of this lesson your company can open the three financial statements under Circular 99, knows how to reconcile them with the ledger, and knows the places that are easy to misread on the sample data. (B01-DN is the balance sheet, B02-DN the profit and loss statement and B03-DN the cash flow statement of the Vietnamese statutory forms.)
Step 1 - The balance sheet
Open the report.
Accounting > Reporting > Statement Reports > Balance Sheet
What you should see: the Report box shows Statement of Financial Position (B01-DN) - C.99, As of a date (10/24/2026 on the screenshot); the lines by code 100, 110, 111, 130, 131, 140... The notice above the report, "There are ... unposted Journal Entries prior or included in this period", refers to draft entries (depreciation and next-period payroll that were prepared in advance); they are not counted.
Step 2 - Reconcile total assets and total equity and liabilities
Scroll down to the part on capital.
Accounting > Reporting > Statement Reports > Balance Sheet
What you should see: TOTAL EQUITY AND LIABILITIES (440 = 300 + 400) equals exactly TOTAL ASSETS (280 = 100 + 200); 1. Contributed capital (411) 20,000,000,000 VND; 10. Retained earnings (420 = 420a + 420b). Your company can check that 411 + 420 on B01-DN equals the balance of account 4111 plus the accumulated profit of the accounts of class 5 to 8 on the ledger. On the screenshot (as of 10/24/2026) both sides come to 65,801,806,093 VND.
Two things to know when reading B01-DN on the sample data:
- 420a = 0, everything is in 420b. The profit of earlier years has not been closed to 4211, so the profit accumulated since 2023 is all on the "current period" line.
- Receivables and payables are shown by partner. A customer's advance payment is shown in 2. Short-term advances from customers (312) and a vendor's advance in 2. Short-term prepayments to suppliers (132), so total assets on B01-DN are larger than the total of the net debit balances of the accounts of classes 1 and 2.
Step 3 - The profit and loss statement
Open the report.
Accounting > Reporting > Statement Reports > Profit and Loss
What you should see: Profit and Loss (B02-DN) - C.99, this year: revenue (01), deductions (02), cost of goods sold (11), selling expenses (25), general administration expenses (26), current corporate income tax expenses (51), profits after enterprise income tax (60). Your company can check that revenue, cost of goods, selling expenses, administration expenses and corporate income tax equal the 2026 movement of accounts 511, 632, 641, 642 and 821 on the ledger.
Step 4 - Compare with the Executive Summary
Open the summary.
Accounting > Reporting > Statement Reports > Executive Summary
What you should see: the blocks Cash, Profitability, Balance Sheet, Performance (profit margins, return on investments) and Position (average debtors days...). The line Net Profit equals exactly Profits after enterprise income tax (60) on B02-DN of the same period, and Cost of Revenue equals line 11.
The two reports show the same figure because at the end of every month the accountant has brought all production costs (622 Direct labor cost, the group 627 Manufacturing overhead) into the product cost or the cost of goods: the part that can be allocated to completed orders is done with the Production Cost Allocation document (lesson Allocate production costs to completed orders), and the rest is closed to 632 with the entry "Kết chuyển chi phí sản xuất chưa phân bổ vào giá vốn" (closing of unallocated production costs into the cost of goods). If these two things are not done at period end, B02-DN will lack those amounts (the B02-DN form has no line for 622 or 627) and the profit on B02-DN will be larger than the Net Profit here. This is sample data: do not compare profit between quarters, because payroll exists only from 07/2026 and the earlier quarters have no labor cost.
Step 5 - The cash flow statement
Open the report.
Accounting > Reporting > Statement Reports > Cash Flow Statement
What you should see: Cash Flow Statement (B03-DN) - C.99 by the direct method: I. Cash flow from operating activities (receipts from customers, payments to suppliers, payments to employees, corporate income tax paid), II. Cash flows from investing activities (payments for fixed assets), III. Cash flows from financing activities; at the end of the report Cash and cash equivalents at the beginning of the period (60) and at the end of the period (70 = 50 + 60 + 61). B03-DN reads only the entries that pass through the cash accounts; a receipt not yet reconciled still sits in 1131 and has no cash flow line, while line 110 of B01-DN already counts 1131.
Lesson 88. The general ledger, the trial balance and the books in the Ministry of Finance form
About 10 minutes. By the end of this lesson your company can open the general ledger and the trial balance and knows where the books S03a, S03b, S38, S07, S08 are.
Step 1 - The general ledger
Open the general ledger.
Accounting > Reporting > Audit Reports > General Ledger
What you should see: one line per account with Debit, Credit and Balance of the current month; click the arrow at the start of a line to open each entry, and click an entry to open the source document.
Step 2 - The trial balance
Open the trial balance.
Accounting > Reporting > Audit Reports > Trial Balance
What you should see: three pairs of columns - Initial Balance, the movement in the period, End Balance (Debit, Credit) - and the level-1 accounts with their child accounts below. This is the place for the month-end check: 1131 and 1132 hold only transactions that have not reached the statement; 154 equals the value of the orders in progress; 621, 622, 627 return to 0 after allocation and closing.
Step 3 - Open the group of books in the Ministry of Finance form
Click the menu Reporting on the Accounting menu bar.
Accounting > Reporting
What you should see: the groups Statement Reports, Audit Reports, Stock Reports, Vietnam Accounting Reports (Account Detail Sheet (S38-DN), General Journal (S03a-DN), Ledger (S03b-DN), Account Cash Book (S07-DN), Account Bank Deposit Book (S08-DN)), Partner Reports, Management, Invoice Lists and Manufacturing Reports.
Step 4 - Export the general journal
Click General Journal (S03a-DN).
Accounting > Reporting > Vietnam Accounting Reports > General Journal (S03a-DN)
What you should see: the dialog GENERAL JOURNAL (S03a-DN): Target Moves (All Posted Entries or All Entries), Start Date and End Date, the list of Journals; click Print Pdf or Print Excel to get the book in the form of the Ministry of Finance. The books S03b, S38, S07 and S08 have similar dialogs.
Lesson 89. Aged receivables and payables
About 5 minutes. By the end of this lesson your company knows which customers owe overdue money and whom the company owes.
Step 1 - Aged receivable
Open the report.
Accounting > Reporting > Partner Reports > Aged Receivable
What you should see: one line per customer, with the columns At Date, 1-30, 31-60, 61-90, 91-120, Older, Total; the Total line at the top. A negative figure (in red) is an advance or overpayment not yet matched to an invoice, as with the deposit of the lesson Reconcile the bank statement. Click the arrow at the start of a line to see each invoice.
Step 2 - Aged payable
Open the report.
Accounting > Reporting > Partner Reports > Aged Payable
What you should see: the same layout for vendors: one vendor per line, split by age; a negative figure (in red) is an advance or an overpayment not yet offset against a bill. The report gathers every payable account by partner: payroll and the contributions on payroll show here only while they are unpaid. To see one vendor only, filter with the Partner box.
Lesson 90. Catalog of accounting reports and print templates
Read in 5 minutes. The Accounting application has 33 report entries on the menu Accounting > Reporting; 7 of them also open in another application (shown in the last column).
| Report | What question it answers | Also in |
|---|---|---|
| Balance Sheet (B01-DN) | Assets, liabilities and capital on one date | - |
| Profit and Loss (B02-DN) | Revenue, cost of goods, expenses and profit in the period | - |
| Cash Flow Statement (B03-DN) | Cash in and out by operating, investing and financing activities | - |
| Executive Summary | Cash, profit, payables and receivables, margins on one page | - |
| Tax Report | Input VAT, output VAT and import tax by period | - |
| General Ledger | Movement and balance of each account, down to the document | - |
| Trial Balance | Opening, movement and closing of every account | - |
| Journal Items Analysis | Filter, group and pivot the journal items by any field | - |
| Product Journal (S10-DN) | Stock in, out and balance of each material in the Ministry of Finance form | Inventory (Warehouse and quality) |
| General Inventory Journal (S11-DN) | Summary of stock in, out and balance by period | Inventory (Warehouse and quality) |
| Stock-In Report | List of stock receipts in the period | Inventory (Warehouse and quality) |
| Stock-Out Report | List of stock issues in the period | Inventory (Warehouse and quality) |
| Stock Card (S12-DN) | Stock card of each item | Inventory (Warehouse and quality) |
| Account Detail Sheet (S38-DN) | Detail of one account in the statutory form | - |
| General Journal (S03a-DN) | Every entry by date | - |
| Ledger (S03b-DN) | The ledger in the form of the Ministry of Finance | - |
| Account Cash Book (S07-DN) | Cash receipts and payments | - |
| Account Bank Deposit Book (S08-DN) | Receipts and payments through the bank | - |
| Partner Ledger | Debt of each partner, document by document | - |
| Aged Receivable | Which customer owes, and how overdue | - |
| Aged Payable | Whom the company owes, and when it is due | - |
| Invoice Analysis | Revenue and invoice value by customer, product, month | - |
| Invoice & Bill Analysis | Compare sales invoices and purchase bills by partner, product | - |
| Analytic Report | Cost and revenue by analytic account (department, project) | - |
| Transfer / Allocation Analysis | The automatic transfer and allocation entries that have run | - |
| Budget Report | Actual against budget | - |
| Assets | List of fixed assets, original cost, remaining value | - |
| Asset Depreciation | Depreciation by month, by asset | - |
| Sales Invoice List (01 -1/GTGT) | The invoice list that goes with the VAT declaration | - |
| Purchase Invoice List (01 - 2/GTGT) | The invoice list that goes with the VAT declaration | - |
| Production Cost Report | Cost by product, period, cost item | Manufacturing (Shop floor production) |
| Subcontracting Report | Ordered, received and remaining; materials supplied and used for subcontracting | Purchase (Subcontracting) |
| Accounting Reports (configuration) | The list of report templates, where the B01, B02, B03 indicators are edited | Accounting > Configuration > Management > Accounting Reports |
The last report in the table is a configuration screen and is not counted in the 33 entries. Besides the menu, a manufacturing order has Cost Analysis and Overview.
Print templates of Accounting (15 templates): Invoice PDF; PDF without Payment; Original Bills; the system-generated invoice archive copy; Journal Entry; Payment Receipt (Template 01-TT/02-TT) on the journal entry and on the payment; Payment Receipt; Statement; Account Asset Card (S23-DN); General Journal (S03a-DN); Ledger (S03b-DN); Account Cash Book (S07-DN); Account Bank Deposit Book (S08-DN); Account Detail Sheet (S38-DN). A print template opens from the gear icon > Print on each document; the reports export PDF and XLSX with the buttons at the top left.
Lesson 91. What the system does not do by itself
Read in 5 minutes. The cost accountant needs to know in advance that the items below are still the work of a person, so as not to wait for the system to do them.
| Item | The system | How the accountant does it |
|---|---|---|
| Period-end closing of 621, 622, 627 | Does not close them by itself | The Production Cost Allocation document brings the movements into completed orders; the rest is closed to 632 with a month-end entry (the demo system has one entry "Kết chuyển chi phí sản xuất chưa phân bổ vào giá vốn" (closing of unallocated production costs into the cost of goods) for each month), or use an automatic transfer template (Accounting > Configuration > Management > Automatic Transfer Models). If this is not done, B02-DN lacks these amounts |
| Calculate the difference between actual payroll and the labor hours already counted in the cost | Does not calculate | The accountant compares 622, 627 on the Trial Balance, then allocates the difference |
| Split direct labor (622) from overhead (627) on the order completion entry | Does not split: each work center has one expense account | See the split on the Production Cost Report |
| Bring actual payroll from the payroll sheet into the cost of each order | Does not: labor hours are counted at the hourly rate of the work center and of the employee | Production cost allocation at the end of the period |
| An OEE indicator with all three components (availability x performance x quality) | Only availability and performance | See Equipment maintenance |
| Hard-block the confirmation or running of an order when there is no approval | An approval request only creates and synchronizes the order and the bill of materials | See Approvals |
| A separate rework order for a finished product that failed; automatically create an empty bill of materials for a code that has none | Not available | Scrap, unbuild, or a new order; a draft order and then create the bill of materials |
| Quarantine and release status on a lot; a print template for the certificate of analysis (COA) | Not available | See Warehouse and quality |
| The month-end VAT offset entry | Does not create it | The accountant posts Debit 33311 / Credit 1331 |
| Closing profit and loss to 4211 at year end | Does not close it | The accountant posts the year-end closing entry |
Lesson 92. Self-study exercise - a month of product cost
About 30 minutes, no step-by-step screenshots.
- Make one order of a Nova frame assembly through to Done (lesson Cost of one order when it is completed). Write down the cost on Cost Analysis and on the Overview of the order; explain the difference with Direct Labor.
- Make a second order and leave it unfinished with 10 minutes on the operation; post the work-in-progress entry on the last day of the month. Calculate by hand beforehand: the value of the components + 10/60 x (210,000 + 41,000); compare with the Debit 154 line the system proposes.
- Open
Accounting > Reporting > Audit Reports > Trial Balancefor last month; write down the end balance of 6274. - Create a Production Cost Allocation document for a 6274 journal item still on the list, split By Current Cost over the Lumi vehicle orders completed in the same month. Read the tab Valuation Adjustments: which vehicle gets more, and why.
- Open the Production Cost Report for that month and find the line Allocated Manufacturing Overhead in the detail of a Lumi model.
- Create a receipt from a dealer, add a bank transaction for the same amount and reconcile. Check that the receipt changes to Paid.