Viindoo demo handbook for manufacturing and assembly

Part VI. Shop floor production

This part answers these questions: how does an assembly order go from creation to the moment the vehicle enters the finished goods warehouse, what does the team leader record right at the line, what does the system block until quality has been checked, and what changes in the warehouse, in accounting and in the product cost when the order is closed. The main readers are the workshop manager, the line team leaders, the planner, the storekeeper who issues materials and the cost accountant. The bills of materials, work centers and hourly rates are set up in the part Manufacturing engineering; overall planning is in the part Production planning; this part starts from the moment a manufacturing order exists.

Every lesson in this part runs on the company "Công ty Cổ phần SX Viindoo" and the warehouse "Nhà máy Yên Mỹ" (Yen My Factory). When you open a path, check that the top right corner shows this company.

The three orders used as examples in this part are orders that this handbook created during its test run:

Order Product Used for
NM1/MO/01219 [XMD-LUMI-TR-TC] Viindoo Lumi Electric Motorbike (Pearl white, Standard), 1 vehicle The order that goes all the way from draft to receipt into stock
NM1/MO/01217 [XMD-AURA-TR-CC] Viindoo Aura Electric Motorbike (Pearl white, Premium), 1 vehicle The missing components situation
NM1/MO/01227 [BTP-KHUNG-AURA] Powder-coated frame assembly - Aura, 3 assemblies The situations of consumption above the bill of materials, scrap, partial production and splitting the order

Your company follows the steps and creates its own new order, and the system issues a different order number. The figures in this handbook (hours, costs, journal entries) belong to the test-run order; your figures will differ according to the minutes actually recorded.

Lesson 41. Shop floor manufacturing configuration

About 15 minutes. By the end of this lesson your company knows which settings make the shop floor work as the following lessons show: work orders, a two-step warehouse, the hourly rate of the work center, the consumption level of the bill of materials and a quality control point that blocks. This lesson is for viewing only; nothing is changed.

Step 1 - Open the Manufacturing settings

Open the settings of the Manufacturing application and look at the Operations block.

PathManufacturing > Configuration > Settings
Manufacturing settings, Operations and Planning blocks

What you should see: the boxes Work Orders, Subcontracting and By-Products are ticked; Work Order Dependencies and Unlock Manufacturing Orders are not ticked. Scroll down to the block Viindoo Manufacturing Features: the boxes Shop Floor Control, Manufacturing Progress Management, MRP Standard Consumption, Manufacturing Standard Consumption Analysis, Manufacturing Backdate, Manufacturing Quality Control and Maintenance - MRP are all ticked.

The table below explains the settings that matter to the shop floor:

Setting Turn it on to What you lose if it is off
Work Orders Each order generates work orders from the bill of materials, schedules each work center and records actual hours The order only has components and finished products: no labor hours, no machine-hour cost, no shop floor screen
Shop Floor Control (block Viindoo Manufacturing Features) The Shop Floor screen for tablets: record work for the right worker, stop the machine, record consumption, close the order at the line The team leader has to record on the manufacturing order screen in the office; labor is costed only at the hourly rate of the work center, not per person
Work Order Dependencies Make a later operation wait for an earlier one in the order declared on the bill of materials Currently off: the operations still run one after another in the order sequence, but you cannot declare a dependency such as "operation 3 waits for both 1 and 2"
Unlock Manufacturing Orders Let manufacturing users edit the quantity to consume without unlocking each order Currently off: to edit the quantity to consume on a confirmed order you must use Lock/Unlock under the gear icon of the order
By-Products The bill of materials can declare by-products and split the cost proportionally By-products cannot be recorded; the report Loss By-products Analysis has no data
Manufacturing Progress Management The Manufacturing Orders Progress screen groups the orders of one demand and computes the percentage complete You only follow orders one by one
MRP Standard Consumption, Manufacturing Standard Consumption Analysis Each bill of materials line has a standard quantity and a loss rate; the report Loss Components Analysis compares actual with standard You cannot measure the consumption difference per component
Manufacturing Backdate When you validate a transfer, scrap or complete an order, the system asks for the date of the operation and lets you back-date it Every operation takes the date and time of the click; you cannot post yesterday's operations afterwards
Manufacturing Quality Control Quality checks are generated per order and per operation; they block starting and finishing an operation and closing the order until the checks are done There are no in-process checks and no finished product checks tied to the order
Maintenance - MRP Equipment is attached to work centers; the maintenance request button on the order and at the shop floor (see Equipment maintenance) A broken machine can only be recorded as a "stop", it does not generate a maintenance request

Trap when configuring on your own: unticking Work Orders and clicking Save archives all the operations of every bill of materials. Ticking it again does not restore them completely. Do not turn this box off on a running system.

Step 2 - See how many steps the warehouse manufactures in

Open the warehouse Nhà máy Yên Mỹ (Yen My Factory) and look at the Manufacture field in the RESUPPLY block.

PathInventory > Configuration > Warehouse Management > Warehouses
The Nhà máy Yên Mỹ warehouse manufacturing in two steps

What you should see: the Manufacture field is set to Pick components then manufacture (2 steps). This means that when you confirm an order the system generates a Pick Components transfer that moves the components from NM1/Tồn kho (stock) to the area NM1/Trước sản xuất (pre-production); the order takes its components from that area. Changing to 1 step or to 3 steps (one more transfer to store the finished products) is only a matter of choosing another value in this field; it is not additional development.

Step 3 - See the hourly rate and the expense account of a work center

Open the work center Tổ khung (Frame team), tab General Information.

PathManufacturing > Configuration > Work Centers
Work center Tổ khung with cost per hour and account 627

What you should see: Cost per hour 210,000 VND per workcenter (machine hour, shown in the Manufacturing overhead column of the cost report), Employee Hourly Cost 41,000 VND per employee (shown in the Direct labor cost column), Overhead Cost Type "Manufacturing Overhead", Direct Labor Cost Type "Direct Labor", Expense Account "627 Manufacturing overhead", Working Hours "Giờ hành chính 40 giờ/tuần" (Office hours, 40 hours/week). These three figures decide the hourly cost in the lesson "Actual hours, cost and journal entries when the order is completed". The other work centers have their own hourly rates: Tổ lắp ráp trên chuyền (Assembly line team) 230,000 VND, Tổ lốp (Tire team) 150,000 VND, Tổ kiểm tra xuất xưởng (Outgoing inspection team) 185,000 VND; each with the same 41,000 VND per employee.

Step 4 - See the consumption level on the bill of materials

Open the bill of materials of the Lumi motorbike, tab Miscellaneous, and look at the Flexible Consumption field.

PathManufacturing > Products > Bills of Materials
Lumi bill of materials, Miscellaneous tab, Flexible Consumption field

What you should see: three choices Allowed, Allowed with warning, Blocked; on the demonstration system the Lumi bill of materials is currently set to Blocked.

Choice When the actual consumption differs from the bill of materials at completion Suited to
Allowed The order closes normally; the difference goes to the loss report Materials that are hard to measure exactly (paint, glue, bolts by the set)
Allowed with warning A warning lists the components that differ and the user must confirm before the order can close Most assembly components
Blocked The order cannot close until the consumed quantity matches the bill of materials; only the manufacturing manager can let it through High-value components with serial numbers (motor, battery)

Each bill of materials carries its own setting, so different vehicles can follow different rules.

Step 5 - See a quality control point that blocks

Open the control point OQC-01.

PathQuality > Quality Control > Quality Controls > Control Points
Control point OQC-01 with the No Proceed if Failed box

What you should see: Title "Match Chassis and Engine Numbers to Label"; Product Templates are the Aura, Lumi and Nova vehicles; Operations "Nhà máy Yên Mỹ: Manufacturing"; the box No Proceed if Failed is ticked; Control Type "All Operations"; Type "Pass - Fail"; To Check (%) 100.00; Team "OQC - Outgoing Inspection"; Responsible Bùi Văn Thành. For the Lumi vehicle, each order generates 4 checks: 3 finished product checks OQC-01, OQC-02 and OQC-03 done when the order is closed, and check OQC-04 "Overall Test Run and Sign-Off of Outgoing Inspection Slip" done before the final inspection operation starts. The control points are set up in the part Warehouse and quality.

Lesson 42. Create the order, confirm it and plan the operations

About 10 minutes. By the end of this lesson your company has created an assembly order for a Lumi vehicle, confirmed it to reserve the components and scheduled the three operations in three teams: Tổ lắp ráp trên chuyền (Assembly line team), Tổ lốp (Tire team) and Tổ kiểm tra xuất xưởng (Outgoing inspection team).

Where a manufacturing order comes from and how to recognise it:

Source When it is generated State when generated How to recognise it on the order
Created by hand The planner clicks New Draft The Source field is empty
Sales order Confirming a sales order for a product that has the Manufacture and Replenish on Order (MTO) routes Confirmed (if there is a bill of materials); Draft if there is no bill of materials yet Source is the sales order number, for example S00063
Reordering rule / Replenishment Stock falls below the minimum Draft, waiting for the planner to confirm Source is the rule code
Master production schedule Clicking replenish on the master schedule Draft Source reads MPS
Parent order A vehicle order needs a semi-finished product (frame assembly, electrical assembly) that is out of stock Confirmed Source is the parent order number
Backorder Completing an order before the full quantity is done Confirmed The order number ends in -002, -003

How orders are generated from a sales order, a reordering rule and the master schedule is covered in the part Production planning.

The states of a manufacturing order:

State Meaning Components reserved yet? Have stock and accounting changed?
Draft Just created, edit freely Not yet Not yet
Confirmed The work orders, the Pick Components transfer and the quality checks have been generated Yes: the Pick Components transfer reserves the components in the warehouse; after that transfer is done, the order reserves the components in the Pre-production area No journal entry yet; components only change location in the warehouse
In Progress At least one operation has been started or a quantity in progress has been recorded Yes No (unless work in progress is posted at period end, see the part Accounting and costing)
To Close All operations are done, waiting for the order to be closed Yes Not yet
Done The order is closed The components have been deducted from stock Yes: material, labor and finished product entries; the finished product is in stock
Cancelled The order is cancelled Released No

The states of a work order: Waiting for another WO (the previous operation is not finished), Waiting for components (the components have not reached the pre-production area), Ready, In Progress, Finished, Cancelled.

Step 1 - Open the list of manufacturing orders

Open the list of manufacturing orders.

PathManufacturing > Operations > Manufacturing Orders
List of manufacturing orders with the To Do filter

What you should see: the list is filtered by To Do, with the columns Reference, Start, Product, Next Activity, Source, Component Status (Available, Not Available, Expected date), Quantity, UoM, Company, Progress, State. The number of rows changes from day to day.

Step 2 - Create a new order and choose the product

Click New. In the Product field type XMD-LUMI-TR-TC and choose "[XMD-LUMI-TR-TC] Viindoo Lumi Electric Motorbike (Pearl white, Standard)". Keep Quantity at 1.00.

PathManufacturing > Operations > Manufacturing Orders
New order with the Lumi vehicle chosen, bill of materials filled in automatically

What you should see: the Bill of Material field fills in automatically with "XMD-LUMI: Viindoo Lumi Electric Motorbike"; the Components tab fills with 21 component lines for the Pearl white color, Standard version (frame assembly, electrical assembly, motor, Pearl white plastic body kit, 5 graphene batteries...), all taken from NM1/Trước sản xuất. One bill of materials is shared by every color and every version; the system picks the right body kit and electrical set for the variant.

Step 3 - Save the draft order

Click the save icon (cloud) next to the order name.

PathManufacturing > Operations > Manufacturing Orders
Order NM1/MO/01219 in the Draft state

What you should see: the order has a number (for example NM1/MO/01277), the status bar is on Draft, and the buttons Confirm, Cancel, Quality Alert and Maintenance Request are shown. In this state the components are not reserved.

Step 4 - Confirm the order

Click Confirm.

PathManufacturing > Operations > Manufacturing Orders
Confirmed order, the Lot/Serial Number field and new buttons appear

What you should see: the state Confirmed; the Component Status field shows Available (all components in stock) or, as in the screenshot, Not Available in red when some component has no stock yet; the smart button bar has Purchases 1 when a purchase was generated for a missing component, Transfers 1 and Quality Checks 4; the Lot/Serial Number field appears (the vehicle is tracked by serial number) and the buttons Produce All, Plan and Start. The history on the right reads "Draft -> Confirmed".

Step 5 - Plan the operations

Open the Work Orders tab, then click Plan on the button bar.

PathManufacturing > Operations > Manufacturing Orders
The three operations have been scheduled

What you should see: three operation lines with the columns Operation, Work Center, Product, Quantity Re..., Expected Duration, Real Duration and Status: Lắp ráp tổng thành trên chuyền (Final assembly on the line; Tổ lắp ráp trên chuyền, 45:00 minutes), Lắp bánh xe, phanh (Fit wheels and brakes; Tổ lốp, 15:00) and Kiểm tra hoàn thiện, đóng số khung (Final inspection and chassis number stamping; Tổ kiểm tra xuất xưởng, 15:00), 75:00 minutes expected in total, all in the status Waiting. The Plan button changes to Unplan; Scheduled Date and Scheduled End jump to the nearest available working slot of the teams. The inspection operation line has a Quality Checks button: this operation has a check that must be done first.

Step 6 - See the schedule by work center

Open the planning screen by work center, type your order number in the search box and choose Search Manufacturing Order for.

PathManufacturing > Planning > Work Orders > Planning by Workcenter
Planning by work center: one group per team

What you should see: the screen Work Orders Planning opens as a Gantt chart, filtered on the states In Progress, Ready, Waiting and Pending, grouped by Work Center and on your order. Each team that has an operation of the order is a group row (in the screenshot Tổ khung) with the operation below it, such as "NM1/MO/01279-002 - Hàn hoàn thiện, sơn tĩnh điện khung", drawn as a bar on its planned date; the red dotted line is today. Remove the order filter to see the whole load of each team; drag and drop a bar to move the schedule; the buttons All, Day, Week, Month, Year change the time scale, and the buttons at the top right switch to the list, calendar, pivot and graph views.

Step 7 - See the schedule by manufacturing order

Open the planning screen by order and filter on the same order as in the previous step.

PathManufacturing > Planning > Work Orders > Planning by Production
Planning by order

What you should see: the same Gantt chart, here grouped by Manufacturing Order: one group row carrying the order number, and below it the operations of the order as bars one after another (one operation in the screenshot). Use this screen to answer "when will this order be finished"; use the work center screen to answer "is this team overloaded".

Step 8 - See the component situation before starting

Go back to the order and click the smart button Overview.

PathManufacturing > Operations > Manufacturing Orders
Manufacturing order overview before production

What you should see: the MO Overview screen has the columns Status, Quantity, Free to use / On Hand, Reserved, Receipt (Available, or the date the goods arrive), MO Cost and BoM Cost. The first line is the finished product (state Ready) and gives the expected cost of the order against the cost according to the bill of materials. A component that shows "Not Available", or an expected date later than the start date, is a component that will delay the order (see the lesson "When reality departs from the plan").

Lesson 43. Issue materials to the shop floor

About 5 minutes. By the end of this lesson the storekeeper has moved the order's components to the pre-production area and the order is ready.

Step 1 - Open the Pick Components transfer of the order

On the order, click the smart button Transfers.

PathManufacturing > Operations > Manufacturing Orders
Pick Components transfer in the Ready state

What you should see: the transfer (for example NM1/PC/01533), Operation Type "Nhà máy Yên Mỹ: Pick Components", Source Location NM1/Tồn kho, Destination Location NM1/Trước sản xuất, Source Document is the order number, and the state is Ready. Every line has the Quantity column equal to the Demand column: the goods are reserved. The transfer form offers the buttons Check Availability, Validate, Print, Return, Cancel and Split Across Trips, and the tabs Operations, Additional Info, Note and Main Equipments; the storekeeper prints the transfer with the Print button to pick the goods.

Step 2 - Validate the transfer

Click Validate. A box asking for the Transfer Date appears (the box title shows "Validate with a Back Date"); keep the current date and time and click Validate.

PathManufacturing > Operations > Manufacturing Orders
Box asking for the effective date when validating a transfer

What you should see: the box has one Transfer Date field already filled with the current date and time. This box appears because the setting Manufacturing Backdate is on: when you need to post yesterday's transfer afterwards, change the date here.

Step 3 - Check that the transfer is done

Look at the transfer again after validating.

PathManufacturing > Operations > Manufacturing Orders
Pick Components transfer in the Done state

What you should see: the status bar is on Done and the Effective Date field has a value. The components are now in the pre-production area; this is an internal transfer, so it generates no journal entry.

Step 4 - Go back to the order and see the reserved components

Click the order number in the breadcrumb at the top to go back to the order.

PathManufacturing > Operations > Manufacturing Orders
Order with components available, components reserved in the pre-production area

What you should see: Component Status changes to Available in green; the Quantity column of each component equals To Consume; the Unreserve button appears. The first operation changes to Ready; the second and third operations stay Waiting for another WO.

Lesson 44. Running the shop floor: start, record labor, stop the machine

About 15 minutes. By the end of this lesson your company has run the first two operations on the shop floor touch screen: recorded labor for the right worker, reported a line stop with a reason, restarted it and completed the operation. This screen is made for a tablet placed at the team; it works the same on a desktop computer.

Step 1 - Open the Shop Floor screen

Click the Shop Floor application tile on the home screen. The first team shown in this lesson is Tổ lắp ráp trên chuyền (Assembly line team).

PathShop Floor
Shop Floor screen of the Tổ lắp ráp trên chuyền team

What you should see: a title with the name of the selected team, a green label with the number of running jobs and a Refresh button, and the filter buttons All, Ready, Running, Waiting, Station stopped with counts; on the left My work centers (with Manage work centers) and the list of Operators; each card is one operation with the order number, product, operation name, Responsible, a progress bar, the line "Output 0.00 / 1.00 Units" and a large button (Open & start, Continue operation). The label on the card is Ready, Running or Waiting for components; a card that waits for components says "Components not available yet - you can start anyway." The number of cards changes from day to day.

Step 2 - Add the order's teams to my work centers

Click Manage work centers, tap Tổ lốp (Tire team) and Tổ kiểm tra xuất xưởng (Outgoing inspection team) (keep Tổ lắp ráp trên chuyền, Assembly line team), then click Add to my work centers.

PathShop Floor
Box for choosing my work centers

What you should see: each team tile shows the number of ready and waiting operations; the three chosen tiles are highlighted and the line below reads "3 work centers selected". After adding, the left column has three teams; click a team name to change the work board. Each tablet at a team normally selects just one team.

Step 3 - Find the order's operation

Select Tổ lắp ráp trên chuyền in the left column. Type the order number in the Search... box and choose Search Manufacturing Order for.

PathShop Floor
Card of the assembly operation of the order, Ready state

What you should see: exactly one card, labeled Ready, with the line "Output 0.00 / 1.00 Units" and the button Open & start.

Step 4 - Open the operation and choose whom to credit

Click Open & start. The operation opens and starts running at once under the account you are logged in with. Click On behalf next to the timer.

PathShop Floor
Box for choosing the person credited

What you should see: the box Who is this operation credited to? with the label Team leaders only, the block Who is credited with three tabs This work center, Recently credited and All employees (each with a count) and the list of workers, and two panels: This action has cost consequences (choosing another person moves both the time and the labor cost to that person's hourly cost, or to the work center's per-employee rate when that person has none) and The time entry keeps both identities (Acting user, the account you are logged in with).

Step 5 - Choose the worker

Tap the name of a worker, for example Bùi Diệu Hoa, then click Back.

PathShop Floor
Credit for Bùi Diệu Hoa selected

What you should see: a blue strip at the top reads "Recording for: Bùi Diệu Hoa" with a Back to me button; the bottom panel now shows Acting user (your account) and Credited to (the worker you chose, who "Receives the time and labour cost"). The time entry keeps both identities. This choice is kept only while the screen stays open; when you open the card again in another session, choose again. The time that ran before the switch stays recorded for your own account.

Step 6 - Check that the operation is running

Click Back to return to the operation.

PathShop Floor
Operation running, timer counting

What you should see: a green Running label and the minute:second timer counting, the button On behalf, the strip "Recording for: Bùi Diệu Hoa" still there; the blocks Output (0.00 / 1.00 Units with Record output), Materials, Call maintenance (machine keeps running) and Instructions (the operation's instruction note, with View drawing full screen); the buttons Record scrap and Record materials used; and at the bottom Pause, Stop machine and Finish operation. The manufacturing order changes to In Progress.

If you pause the operation, the button Pause changes to Resume; choose On behalf again if the next person is different.

Step 7 - Report a machine stop with a reason

Click Stop machine.

PathShop Floor
Box What's happening? with the stop reasons

What you should see: the box What's happening? with the line "Tap a tile to report right away - there is no confirmation step. Tapped the wrong one? A supervisor can put the station back to work - nothing is lost."; the block Other reason with six tiles Material Availability, Missing Components, Waiting for Quality Inspection, Setup and Adjustments, Process Defect, Reduced Yield; a red button Equipment failure - call maintenance (see Equipment maintenance); and an optional block Additional details with the tiles Out of stock, Wrong material size, Material surface defect, Waiting for another team to deliver and Type a description.

Step 8 - Choose the stop reason

Tap Setup and Adjustments.

PathShop Floor
Station stopped with the reason Setup and Adjustments

What you should see: a red strip at the bottom "Station stopped: Setup and Adjustments" and the button Restart station. The whole work center switches to stopped, not just this order.

Note for team leaders: reporting a station stop stops every operation running at that station, including those of other orders. Their timers stop too and they switch to paused; when the station restarts, the person doing each operation must resume it. Before reporting a stop, look at the Running filter button of the station to see who will be affected. The stop time is counted by the working calendar of the station (Giờ hành chính 40 giờ/tuần): a stop outside working hours, for example on Saturday, records 0 minutes of loss.

Step 9 - See the work board while the station is stopped

Click Back to leave to the team's work board.

PathShop Floor
Work board: card with the Station stopped label

What you should see: the filter button Station stopped · 1; the card has a red Station stopped label and a yellow button Open to handle incident. The blue strip "Recording for: Bùi Diệu Hoa" is still shown at the top of the board with its Back to me button. The workshop manager looking at this board knows at once which team is standing still.

Step 10 - Restart the station

Click Open to handle incident, then click Yes, restart.

PathShop Floor
Confirmation to restart the station

What you should see: a red frame "Station stopped: Setup and Adjustments" with the line "Restart it with Restart station once the cause is fixed.", the question Restart this station? and two buttons Keep it stopped and Yes, restart. While the station is stopped, Record output, Pause and Finish operation are all locked ("Work center Tổ lắp ráp trên chuyền is stopped, so this operation cannot be paused or finished."), and the operation label reads Station stopped. Restarting a station is the manager's job; a worker who tapped the wrong tile loses no data.

Step 11 - Confirm the restart

Click Yes, restart.

PathShop Floor
Station running again, operation paused

What you should see: the red frame disappears; the operation label reads Operation paused, and the buttons Resume, Stop machine and Finish operation work again. Click Resume (choose On behalf again if needed) so that the worker carries on.

Step 12 - Finish the assembly operation

When the team is done, click Finish operation.

PathShop Floor
The assembly operation card has left the team's board

What you should see: the operation panel closes; the board of Tổ lắp ráp trên chuyền no longer has the order's card (All · 0 and "No data to display" while filtered by the order), and the next operation shows one card at Tổ lốp. The operation Lắp bánh xe, phanh of Tổ lốp changes to Ready.

Step 13 - Run the second operation at Tổ lốp

Select Tổ lốp (Tire team) in the left column, find the order, click Open & start, choose On behalf for a worker (for example Bùi Hữu Tuấn). When done, click Finish operation.

PathShop Floor
Operation Lắp bánh xe, phanh running, labor credited to Bùi Hữu Tuấn

What you should see: "Recording for: Bùi Hữu Tuấn", the Running label, the operation name "Lắp bánh xe, phanh". From the moment you choose the worker, the operation time is credited to that worker. After it is finished, the final inspection operation changes to Ready.

Lesson 45. Quality checks on the line, recording consumption, assigning the chassis number and closing the order

About 15 minutes. By the end of this lesson the vehicle has passed the in-process check, the components actually used have been recorded, the chassis number has been assigned, the vehicle has passed the finished product checks and entered stock. Your company will also see for itself how the system blocks when the checks have not been done.

Step 1 - Open the final inspection operation

Select Tổ kiểm tra xuất xưởng (Outgoing inspection team) in the left column and find the order.

PathShop Floor
Card that says a quality check must be done first

What you should see: the card of the operation "Kiểm tra hoàn thiện, đóng số khung" (Final inspection and chassis number stamping) is labeled Ready and has a yellow label 1 quality check(s) to do first, the button reads Open & do quality checks, and the line below reads "Record the quality checks first: Overall Test Run and Sign-Off of Outgoing Inspection Slip."

Step 2 - Try to start before the check is done

Click Open & do quality checks.

PathShop Floor
Quality checks screen before starting, the Start the operation button is locked

What you should see: the screen Quality checks before you start with the block Quality steps, "1 step(s) still to record", and the step Overall Test Run and Sign-Off of Outgoing Inspection Slip with the label To do and the buttons Pass, Fail, Add a note to the Fail, Take photo, Report quality issue and Reopen (dimmed). The button Start the operation is dimmed and cannot be clicked: no check, no work.

Step 3 - Record Pass and start the operation

Click Pass, then click Start the operation.

PathShop Floor
Inspection operation running, list of materials

What you should see: the operation is Running; the block Output shows 0.00 / 1.00 Units with "Finished lot" and the lot number (the chassis number once it has been assigned, see Step 5) and Record output; the block Materials lists the order's components with Expected, Actual, the unit and the label ✓ Enough; the Quality steps block on the right shows the check as Passed; the buttons at the bottom are Pause, Stop machine and Finish operation. If a component has no recorded quantity yet, a yellow label ▲ 1 material(s) still short appears, Finish operation is dimmed and the last line reads "1 material(s) still need a recorded quantity (enter 0 if none was used): [LK0132] Viindoo Outgoing Inspection Slip". If you had clicked Fail in the previous step, the system would record a failed check and still block, because the control point has No Proceed if Failed.

Step 4 - Record the consumption of a missing component

Scroll the Materials block to the line [LK0132] Viindoo Outgoing Inspection Slip and tap that line. Tap As expected: 1.00 Units (or type the quantity actually used on the numeric keypad), then click Confirm consumption.

PathShop Floor
Keypad for recording the actual consumed quantity

What you should see: the consumption screen for the component with Expected 1.00 and Actual (the quantity recorded so far), a large figure being entered, the button As expected: 1.00 Units, the keypad, and at the bottom Cancel and Confirm consumption with the line "Actual after recording: 1.00 of 1.00 Units". After you confirm, the screen Record material consumption lists every component with the label ✓ Enough; click Back to operation to return. The button Record materials used in the operation panel opens the same screen, together with Add a component outside the bill of materials for when you have to use an extra component that is not on the bill of materials. For a component that was used and spoiled, click Record scrap (see the lesson "When reality departs from the plan").

Step 5 - Type the chassis number as the serial number of the vehicle

On the office computer or at the team, open the manufacturing order, type the chassis number stamped on the vehicle in the Lot/Serial Number field (for example RLVLM26K23001), choose Create "RLVLM26K23001" and click the save icon.

PathManufacturing > Operations > Manufacturing Orders
Typing the chassis number in the Lot/Serial Number field

What you should see: the suggestion list has Create "RLVLM26K23001" and Create and edit.... After saving:

Order carrying the chassis number RLVLM26K23001

the Lot/Serial Number field shows RLVLM26K23001 and Progress shows the percentage reached. The shop floor screen has no field for typing a serial number, only Auto-generate lot (a sequential number such as 0000003) or choosing an existing number; chassis and engine numbers follow the factory's own convention, so type them on the order as in this step, before recording the finished product.

Assign the chassis number before recording the finished product. In the test run, Auto-generate lot was clicked first and the number was changed to the chassis number afterwards: the 3 finished product checks still carried the old automatic number (0000003) while the vehicle received into stock carried the new chassis number. Keep this in mind when operating (see the table of problems at the end of the handbook).

Engine number: for the Premium version vehicles (Aura, Lumi), the hub motor and the lithium battery are managed by lot; the motor and battery lot numbers are recorded on the component line of the order and can be traced from the chassis number (lesson "Actual hours, cost and journal entries when the order is completed", traceability step). Standard version vehicles use a motor that is not managed by lot, and the engine number is matched at the check OQC-01.

Step 6 - Record the finished product on the shop floor

Go back to the shop floor screen, open the operation again (Continue operation) and click Record output. Tap 1.00 to enter the quantity just made, check that Assigned lot is the chassis number, then click Confirm output.

PathShop Floor
Recording the finished product with the assigned lot being the chassis number

What you should see: the screen Record output with the panel Quantity just made (1.00 Units, "Recorded 0.00 / 1.00 Units - enter the quantity you have just made", "Tracked by serial number: record exactly 1 unit, once." and "After this recording: 1.00 / 1.00 Units") and the panel Finished lot with the button Auto-generate lot, Assigned lot RLVLM26K23001 and the list "Or pick an existing lot"; at the bottom Cancel and Confirm output. After you confirm:

1 vehicle recorded, with an Undo button

the screen shows the panel One serial-numbered unit per order ("This order makes one serial-numbered unit, and it is recorded (1.00 / 1.00 Units). Finish the operation and close the order.") and the panel Undo the last recording with an Undo button ("Undo removes 1.00 Units from the order."), used when you record by mistake while the order is still open. Click Back to the operation.

Step 7 - Finish the last operation

PathManufacturing > Operations > Manufacturing Orders

Click Finish operation.

PathShop Floor
Confirm Closing the Production Order screen, 3 finished product checks left

What you should see: the screen Confirm Closing the Production Order with the label Awaiting confirmation, the panel The order closes with these figures (Product, Output recorded 1.00 / 1.00 Units, Finished lot RLVLM26K23001), the warning This action cannot be undone ("Confirming will close manufacturing order NM1/MO/01277. After that, quantities, lots and materials can no longer be changed from the shop floor. If anything is wrong, tap Back - nothing changes."), and the block Finished product checks "3 step(s) still to record": Match Chassis and Engine Numbers to Label, Test Brakes, Lights, Horn and Instrument Cluster, Paint Appearance and Plastic Assembly, each with the label To do. The button Confirm closing order NM1/MO/01277 is dimmed, next to Back, not yet closed, and the last line says it is waiting for Bùi Văn Thành to check. The manufacturing order is now in the state To Close.

Step 8 - Try to close the order before the finished product is checked

To see the system block for yourself, open the order on the computer and click Produce All.

PathManufacturing > Operations > Manufacturing Orders
Invalid Operation box when the finished product has not been checked

What you should see: the box Invalid Operation: "Please do the quality checks first: Match Chassis and Engine Numbers to Label (waiting for Bùi Văn Thành), Test Brakes, Lights, Horn and Instrument Cluster (waiting for Bùi Văn Thành), Paint Appearance and Plastic Assembly (waiting for Bùi Văn Thành)." The order stays in To Close and nothing has entered stock. Click Close.

Step 9 - Check the finished product

Go back to the shop floor screen; on the order card (label Waiting to be closed) click Close the order. Click Pass for all three checks.

PathShop Floor
Three finished product checks Passed, the Confirm closing order button lit up

What you should see: each step has a green label Passed; the button Confirm closing order NM1/MO/01277 can now be clicked, with the line "This cannot be undone." underneath. If a step is Fail, the button stays locked, because the finished product control points all have No Proceed if Failed; the vehicle must be repaired and checked again (click Reopen on that step), or raise a quality alert with Report quality issue.

Step 10 - Confirm closing the order

Click Confirm closing order NM1/MO/01277 (your company's order number).

PathShop Floor
Order closed, 1 unit produced

What you should see: the three finished product checks stay listed as Passed and only a Done button is left at the bottom; click it. The card leaves the team's board and the manufacturing order is Done with 1.00 Units produced.

Step 11 - See the completed order

Open the order again on the computer.

PathManufacturing > Operations > Manufacturing Orders
Order in the Done state

What you should see: the status bar is on Done; every component line has the Consumed box ticked; the smart button bar now also has Traceability, Loss Components Analysis, Loss By-products Analysis, Product Moves, Overview, and under More there are Cost Analysis and Journal Entries; the button Unbuild appears (used when you have to take the vehicle apart to recover components). The history lists the changes of state through Confirmed, In Progress, To Close and Done.

Lesson 46. Actual hours, cost and journal entries when the order is completed

About 10 minutes. By the end of this lesson your company can read how many minutes the vehicle took at each team, what the cost consists of, and which journal entries accounting has posted. The lesson is for viewing only; nothing more is created.

Step 1 - See the actual hours of each operation

On the order, open the Work Orders tab, click the open icon at the end of the line Kiểm tra hoàn thiện, đóng số khung (Final inspection and chassis number stamping), and choose the tab Time Tracking.

PathManufacturing > Operations > Manufacturing Orders
Time Tracking tab of an operation

What you should see: the operation opens as the box Work Orders with its status bar (here Finished), the fields Work Order, Work Center, Product, Quantity, Lot/Serial Number, Manufacturing Order, Start Date and Expected Duration, and the tabs Time Tracking, Components and Work Instruction. In Time Tracking, each click of start - pause - finish is one line with User, Employee, Duration, Start Date, End Date and Productivity (for example "Fully Productive Time"), and the total Real Duration is shown below. The test-run order: the assembly operation 4 minutes, wheel fitting 1.05 minutes, inspection 4.37 minutes; a total of 9 minutes 25 seconds against 75 minutes expected (very quick because they were clicked as a trial). The workshop manager can edit a line or Add a line when a worker forgot to click; the hours here are the hours used to compute the cost.

The Work Orders table on the order shows a duration of 3.9999 minutes as "03:60" because of display rounding; the number of minutes used for costing is still exactly 4 minutes.

Step 2 - See the order overview after completion

Click the smart button Overview.

PathManufacturing > Operations > Manufacturing Orders
Manufacturing order overview after completion

What you should see: the columns Unit Cost and Real Cost of each component; on the first line (the finished product) Unit Cost 9,004,864 VND, the cost at which the vehicle was received, and Real Cost 8,998,427 VND. This screen only adds the machine hours at the hourly rate of the work center; it does not yet add the labor part per person; the real receipt cost (9,004,864 VND) is seen in the next step.

Step 3 - See the cost analysis by item

Click More on the smart button bar and choose Cost Analysis.

PathManufacturing > Operations > Manufacturing Orders
Production cost analysis of the order

What you should see: the page Production Cost Analysis with "Total Quantity: 1.00 Units, from 1 manufacturing order(s)", Total Cost 9,004,864 VND and Unit Cost 9,004,864 VND, divided into three blocks: Direct Materials Costs 8,967,005 VND (a table with Materials, Manufacturing Orders, Standard Quantity, Actual Consumption Quantity, Unit Cost, Cost Share (%) and Total Cost), Direct Labor 6,437 VND, Manufacturing Overheads 31,422 VND. This button can only be opened once the order is completed.

The cost is computed as follows:

Item How it is computed Test-run order
Direct materials Actual consumed quantity x average cost of each component 8,967,005 VND
Manufacturing overhead (machine hours) Actual hours of the operation x Cost per hour of the work center 4/60 x 230,000 + 1.05/60 x 150,000 + 4.37/60 x 185,000 = 31,422 VND
Direct labor Actual hours of each person x that person's hourly rate; for a person with no rate declared, the 41,000 VND of the work center; stop time is not counted 9.42/60 x 41,000 = 6,437 VND
Cost of the vehicle received into stock Sum of the three items 9,004,864 VND

The actual salary from the payroll does not go into the cost of each order automatically; the difference between the actual salary and the hours already costed is allocated by the accountant at period end with the production cost allocation (see the part Accounting and costing).

Step 4 - See the list of journal entries of the order

Click More, choose Journal Entries.

PathManufacturing > Operations > Manufacturing Orders
23 journal entries generated when the order is completed

What you should see: 23 journal entries with the columns Date, Number, Partner, Reference, Journal, Company, Total and Status, all in the Inventory Valuation journal, state Posted, all on the date the order was completed: 21 entries for issuing each component, one entry "NM1/MO/01219 - Xe máy điện Viindoo Lumi" (receipt of the finished product) and one entry "NM1/MO/01219 - Nhân công" (labor); the references are generated in Vietnamese.

Step 5 - Open the labor journal entry

Click the line "NM1/MO/01219 - Nhân công".

PathManufacturing > Operations > Manufacturing Orders
Labor journal entry Debit 154 / Credit 627

What you should see: two lines: Debit 154 Work in progress 37,860 VND; Credit 627 Manufacturing overhead 37,860 VND. Account 627 comes from the Expense Account of the work center (lesson "Shop floor manufacturing configuration", Step 3). Machine hours and person hours are posted in one entry to one account; splitting direct labor from manufacturing overhead is done in the cost report, not in the journal entry.

Step 6 - Open the finished product receipt entry

Go back to the list and click the line "NM1/MO/01219 - Xe máy điện Viindoo Lumi".

PathManufacturing > Operations > Manufacturing Orders
Finished product receipt entry Debit 155 / Credit 154

What you should see: Debit 155 Finished goods 9,004,864 VND; Credit 154 Work in progress 9,004,864 VND. Account 154 of the order returns to 0: materials and labor go to the debit side, the finished product comes out on the credit side.

Table of consequences when the order is closed (test-run order NM1/MO/01219):

Where What changes Figures
Warehouse 21 component lines deducted from NM1/Trước sản xuất; 1 vehicle with chassis number RLVLM26J24001 received into NM1/Tồn kho Stock of the Lumi Pearl white Standard vehicle goes up by 1
Accounting - materials 19 components: Debit 154 / Credit 152; 2 semi-finished products (frame assembly, electrical assembly): Debit 154 / Credit 155 Credit 152: 7,182,987 VND; Credit 155: 1,784,017 VND
Accounting - labor hours Debit 154 / Credit 627 37,860 VND
Accounting - finished product Debit 155 / Credit 154 9,004,864 VND
Cost The average cost of the Lumi Pearl white Standard vehicle is recomputed with the receipt cost of 9,004,864 VND See Cost Analysis
Quality The 4 checks of the order are Pass Quality > Reporting > Quality Checks
Reports The order appears in the Production Cost Report, Loss Components Analysis, Work Orders, Overall Equipment Effectiveness, Shop Floor Entries Lesson "Shop floor manufacturing reports"

Step 7 - Trace the vehicle by chassis number

On the order, click Traceability.

PathManufacturing > Operations > Manufacturing Orders
Traceability report of the chassis number

What you should see: the Traceability Report has a line with the order, product, date, Lot/Serial # RLVLM26J24001, going from Production into "Tồn kho" (stock), 1.00 Unit; the columns are Reference, Product, Date, Lot/Serial #, From, To and Quantity. Click the arrow at the start of the line to open the details of the order's moves; for a Premium vehicle, components managed by lot (hub motor, lithium battery) show their lot numbers here. Tracing backwards from the chassis number when a dealer reports a defect is covered in the part Warranty and repairs.

Lesson 47. When reality departs from the plan

About 15 minutes. By the end of this lesson your company has met and handled the three most common situations: missing components, using more material than the bill of materials with spoiled goods that must be scrapped, and making less than the full quantity so that the remainder must be split into a new order.

Step 1 - Recognise an order with missing components

Create an order for 1 vehicle "[XMD-AURA-TR-CC] Viindoo Aura Electric Motorbike (Pearl white, Premium)", click Confirm, then click the smart button Transfers and scroll to the bottom of the component list.

PathManufacturing > Operations > Manufacturing Orders
Pick Components transfer missing the motor and the battery

What you should see: the lines whose Quantity is lower than Demand, with a red forecast icon, are the components for which the main warehouse has no more unreserved stock; the other lines are fully reserved. Stock quantities change from day to day, so your company may see other missing components.

This is correct behavior, not an error. Note that on the order, the Component Status field still shows "Available" because the system counts the goods in the pre-production area and the goods reserved for other orders; the reliable figure is in the Pick Components transfer and in the Reserved column of the Overview of the order. Ways to handle it:

Way What to do
Wait for the goods Leave the Pick Components transfer waiting; when the purchase receipt is done, click Check availability on the Pick Components transfer to reserve the goods
Buy the missing part Open Inventory > Operations > Procurement > Replenishment to place a purchase (see the part Purchasing and import)
Move goods from another order Click Unreserve on the less urgent order, then Check availability on the order that must be done first (see the part Warehouse and quality: reserving components for the line)
Make part of the quantity Take the part that is in stock, produce first the quantity for which components are complete, and split off the remainder (Steps 7 - 9)
Cancel the order Click Cancel and confirm; the reserved components are returned to stock

Step 2 - Cancel an order that lacks goods

On the Aura order you just created, click Cancel, then click Confirm in the confirmation box.

PathManufacturing > Operations > Manufacturing Orders
Order lacking goods has been cancelled

What you should see: the status bar is on Cancelled; the accompanying Pick Components transfer is cancelled too; the components that were reserved are released for other orders to use.

Step 3 - Create a semi-finished product order for 3 assemblies

Create a new order for "[BTP-KHUNG-AURA] Powder-coated frame assembly - Aura", Quantity 3, and click Confirm.

PathManufacturing > Operations > Manufacturing Orders
Frame assembly order for 3 assemblies has been confirmed

What you should see: 7 component lines (vehicle frame, rear swingarm, A-leg, side stand, rear shock absorber, bolt set, powder coating for the frame), with To Consume equal to the bill of materials quantity multiplied by the order quantity (the screenshot shows a larger order of 15 assemblies; with 3 assemblies the quantities are three times the bill of materials). Open Transfers, click Validate as in the lesson "Issue materials to the shop floor" to bring the components to the pre-production area, then go back to the order and click Start.

Step 4 - Record the scrap of a spoiled frame

On the order, click the gear icon next to the order number and choose Scrap. Choose as Product a component of the order (for example "[LK0070] Mira Motorbike Frame"), Quantity 1, click Scrap Products; in the box asking for the Actual Scrap Date click Validate.

PathManufacturing > Operations > Manufacturing Orders
Scrap Products box tied to the order

What you should see: the box Scrap Products with the fields Product, Quantity, Scrap Reason, Package, Source Location NM1/Trước sản xuất, Scrap Location "Virtual Locations/Scrap" and Replenish Quantities, and the buttons Scrap Products and Discard; it only lets you choose components of the order. The Scrap Reason field is empty because the company has not declared a list of reasons; your company can type to create a new reason.

Another way in: at the shop floor, click Record scrap in the operation panel.

Step 5 - Check the scrap document

Open the scrap document you just created.

PathManufacturing > Operations > Scrap
Scrap document SP/00001 done

What you should see: the Scrap Orders document (for example SP/00001) in the state Done, with Product "[LK0070] Mira Motorbike Frame", Quantity 1.00, Manufacturing Order the frame assembly order, Source Location, Scrap Location and Date, and the smart button Product Moves. The order gets two more smart buttons, Scraps 1 and Journal Entries 1. The journal entry of the document: Debit 632 / Credit 152 at the cost of the frame (549,000 VND in the test run).

Step 6 - Record the quantity in progress as 2

On the order, edit the quantity-in-progress field (the field to the left of the "/" on the Quantity line) to 2.

PathManufacturing > Operations > Manufacturing Orders
Order records 2 / 3 assemblies, components recomputed for 2 assemblies

What you should see: Quantity 2.00 / 3.00; the To Consume column of each line reads for example "2.00 / 3.00" (the paint line reads 1.94 / 2.91); the Quantity column is recomputed for 2 assemblies; Progress 67 %.

Step 7 - Edit the actual paint consumption

Click the Quantity cell of the line [SON-TD-KHUNG] Powder Coating for Frame (kg), type 2.3 (2.3 kg was actually sprayed for 2 assemblies instead of the 1.94 kg of the bill of materials), then save.

PathManufacturing > Operations > Manufacturing Orders
Paint line 2.30 kg, shown in orange because it exceeds the bill of materials

What you should see: the paint line shows 2.30 in orange (above the To Consume quantity of 1.94 / 2.91), and the Consumed box is ticked. Because the frame assembly's bill of materials is set to Allowed, the order does not ask again; with a bill of materials set to Allowed with warning the system lists the components that differ for confirmation, and with Blocked it does not let the order close.

Step 8 - Complete the part already made

Click Produce on the button bar, and click Validate in the Date Done? box.

PathManufacturing > Operations > Manufacturing Orders
Box You produced less than initial demand

What you should see: the box You produced less than initial demand ("Create a backorder if you expect to process the remaining products later. Do not create a backorder if you will not process the remaining products.") with three buttons Create backorder, No Backorder and Discard.

Step 9 - Split the remainder into a new order

Click Create backorder.

PathManufacturing > Operations > Manufacturing Orders
Backorder NM1/MO/01227-002 for 1 assembly

What you should see: the original order is renumbered (-001), Done with 2 assemblies; the new order (-002) for 1 assembly is Confirmed, with the smart buttons Backorders 2 and Transfers 1 and Overview Progress 66.67 %. The paint line of the new order has 0.97 to consume but only 0.61 reserved (the paint left after the 2.30 kg already used), so Component Status shows "Available" in orange: you must reserve more paint with Check availability before doing the work. This is the correct consequence of using too much. The test-run order later cancelled the backorder to return the components.

The result of the deviating order is read in Loss Components Analysis (a pivot table filtered on the state Done and on the test-run order NM1/MO/01227):

Loss Components Analysis of the frame assembly order
Component Standard Quantity Actual Consumption Qty. Actual Loss Rate (%)
[LK0070] Mira Motorbike Frame 2.00 3.00 (including 1 scrapped frame) 50 %
Powder Coating for Frame (kg) 2.00 2.30 15 %
The five remaining components exactly the standard exactly the standard 0 %

The cost of the 2 assemblies received into stock (Debit 155 / Credit 154) is 2,428,900 VND, including the paint used above the standard; the spoiled frame does not go into the product cost but into the cost of goods sold through the scrap document. An operation that is not timed on the shop floor is recorded at exactly the expected duration when the order is completed (30 minutes, labor cost 125,500 VND).

Lesson 48. Shop floor manufacturing reports

About 10 minutes. By the end of this lesson your company knows which report to open to answer which question about the shop floor. The lesson is for viewing only; nothing is created.

The shop floor manufacturing part has 15 report screens and 5 print templates:

Report Path Which question it answers
Manufacturing Overview (work centers) Manufacturing > Overview Which team has work today, how many operations are to launch, are running, the performance figure of each team
Manufacturing Orders Progress Manufacturing > Operations > Manufacturing Orders Progress How many percent of each demand has been made, how much is left, which orders are late
Work Orders Manufacturing > Reporting > Work Orders Expected workload of each team, expected duration against actual
Overall Equipment Effectiveness Manufacturing > Reporting > Overall Equipment Effectiveness How many hours each team ran, how many hours were lost to each stop reason
Loss Components Analysis Manufacturing > Reporting > Loss Components Analysis Which component was used above the bill of materials, by how many percent
Loss By-products Analysis Manufacturing > Reporting > Loss By-products Analysis By-products obtained against the bill of materials (company 1 has no by-product bill of materials yet, so the screen is empty)
Shop Floor Entries Manufacturing > Reporting > Shop Floor Entries Who recorded what at the shop floor, credited to whom, whether it was undone
Production Cost Report Manufacturing > Reporting > Production Cost Report Cost by product and period, split into materials, labor and overhead (read in the part Accounting and costing)
Manufacturing order overview The Overview button on the order Does this order have enough components, the cost of the order against the bill of materials
Cost Analysis Button More > Cost Analysis on a completed order What the cost of the vehicle consists of
Overview Progress The Overview Progress button on the order How much the order and its child orders have made
Traceability Button on a completed order Which components and lots this chassis number was made from
Planning by order / by work center Manufacturing > Planning > Work Orders > Planning by Production; Manufacturing > Planning > Work Orders > Planning by Workcenter This week's shop schedule, which team is overloaded
Quality Checks Quality > Reporting > Quality Checks Which vehicle has passed which checks, who checked (in full in the part Warehouse and quality)
Scrap Manufacturing > Operations > Scrap Which goods were scrapped in production, on which order

Print templates from the order (gear button > Print): Production Order, Finished Product Label (PDF), Finished Product Label (ZPL) for the label printer, MO Overview; from the work order: Work Order. The Production Cost Report has an Export XLSX button; list screens can be exported by selecting rows and then using Actions > Export.

Step 1 - See the progress of manufacturing orders

Open the progress screen.

PathManufacturing > Operations > Manufacturing Orders Progress
Manufacturing orders progress

What you should see: each row is a demand with Deadline, Quantity To Produce, Quantity Produced, Quantity Remaining, a Progress bar and State (Confirmed, In Progress, To Close). An order in To Close is one that has been made but not closed: open it and close it right away so that the finished product enters stock.

Step 2 - See the work center overview

Click the Overview menu.

PathManufacturing > Overview
Work center overview

What you should see: each team has a tile with the button WORK ORDERS or PLAN ORDERS, the figures To Launch, In Progress, the OEE figure and a weekly load chart. Click a tile to go straight to the team's list of operations.

Step 3 - See the workload by team

Open the work orders report.

PathManufacturing > Reporting > Work Orders
Chart of the expected duration of unfinished operations by team

What you should see: a bar chart of the Expected Duration (minutes) of the operations that are Ready, Waiting, Pending and In Progress, grouped by Work Center. Change Measures to the actual duration, or remove the state filter to see the finished operations.

Step 4 - See equipment effectiveness and losses

Open the overall equipment effectiveness report.

PathManufacturing > Reporting > Overall Equipment Effectiveness
Overall equipment effectiveness by team and loss reason

What you should see: stacked columns by Workcenter > Loss Reason: the part "Fully Productive Time" and the loss parts (Equipment Failure, Missing Components, Setup and Adjustments, Reduced Speed, Waiting for Quality Inspection). The system's equipment effectiveness figure equals the running time divided by (running + stopped) over the most recent month; the system does not compute the full three-component figure of availability x performance x quality.

Step 5 - See the shop floor entries

Open the shop floor entries.

PathManufacturing > Reporting > Shop Floor Entries
Shop floor entries: every action at the shop floor screen

What you should see: each row is one action with Date, Manufacturing Order, Work Order, Kind (Incident, Consumption, Lot Generation, Production, Close Order, Breakdown...), Quantity Produced, Recorded By, Credited Employee, Status. This is the audit log when the shop floor figures are in doubt.

Step 6 - See the checks of an order

Open the quality checks and search by manufacturing order.

PathQuality > Quality Control > Quality Controls > Quality Checks
Four checks of the order, all Passed

What you should see: four QC cards of the order, labeled Passed, each with the Control Point, the Product, the Lot (when the check has one), the Team and the time of the check; the filter on the order shows as Production Order. In the test run, the three finished product checks carried the number 0000003 instead of the chassis number (see the note in the lesson "Quality checks on the line, recording consumption, assigning the chassis number and closing the order", Step 5).

Lesson 49. Exercise: complete an assembly order on your own

About 30 minutes. Your company proves for itself that the shop floor works without looking at each image.

  1. Create an order for 1 vehicle "[XDD-NOVA-TR] Viindoo Nova Electric Bicycle (Pearl white)" (or a Standard version variant of the Lumi vehicle that still has all its components), confirm it and plan it. Write down the expected dates of the three operations on the planning screen by work center.
  2. Open the Overview of the order, and note which components are "Available" and which are not. If any are missing, handle them using the table in the lesson "When reality departs from the plan".
  3. Validate the Pick Components transfer; check that the order changes to Available in green.
  4. On Shop Floor: run the assembly operation crediting one worker, only when the station shows Running · 0 apart from your own operation, report a Missing Components stop for 1 minute and then restart the station, finish it; run the wheel fitting operation.
  5. At the inspection operation: try clicking Start the operation before the check is done (it must be locked), record Pass, record the consumption of the missing component.
  6. Type your company's chassis number in the Lot/Serial Number field on the order, record the finished product at the shop floor, finish the operation.
  7. Try Produce All on the order before checking the finished product and read the blocking box; then check the finished product Pass and close the order at the shop floor.
  8. Open Cost Analysis and Journal Entries: add up materials + labor + overhead yourself and compare with the entry Debit 155 / Credit 154; check that the labor entry credits 627.
  9. Open Shop Floor Entries and Overall Equipment Effectiveness, and find your own machine stop again.

Self-assessment: if you did it correctly the order is Done, the vehicle stock has gone up by 1, and the total of the Debit 154 entries of the order equals the Credit 154 entry of the finished product receipt.